Kenosha County residents will see higher electric bills after the Wisconsin Public Service Commission (PSC) voted on Nov. 5, 2026 to let We Energies recover the full cost of the Paris Solar‑Battery Park, a large‑scale renewable‑energy project in the Town of Paris.
According to Kenosha County Eye, the project was originally approved in 2022 at an estimated $433 million. By the time the solar facility began operating in Dec. 2024 and the battery storage system followed in June 2025, costs had risen to nearly 40% above that figure, creating an unapproved spending gap of $166 million.
The PSC decision allows the utility to pass the entire cost increase onto ratepayers, but it bars We Energies from earning a shareholder return on the $166 million overrun. Commission staff noted that the disputed expenses would increase We Energies’ annual electric revenue requirements in the upcoming rate years.
Consumer advocates, represented by the Citizens Utility Board (CUB), argued that the overruns exceeded both the authorized budget and typical industry cost growth. CUB urged commissioners to reject the excess spending entirely or at least limit the amount recoverable from customers. In its filing, CUB highlighted a lack of timely disclosure from the utility.
We Energies countered that the higher costs stemmed from factors beyond its control, including global supply‑chain disruptions after the COVID‑19 pandemic, labor shortages, and federal restrictions on solar panels made with forced labor. The utility said it mitigated expenses by delaying certain contracts, reallocating labor, and negotiating a settlement on solar panel pricing.
PSC Commissioner Marcus Hawkins criticized the utility for not adequately accounting for known risks when it sought approval to purchase the project, warning that customers should not be left exposed to unexpected expenses. The commission’s 274‑page October 21 decision matrix, filed under docket 5‑UR‑112, detailed the dispute between We Energies, state staff, and consumer advocates over the adequacy of the utility’s cost explanations.
The Paris project, developed by Invenergy and later acquired by We Energies, Wisconsin Public Service Corporation, and Madison Gas and Electric, comprises roughly 200 megawatts of solar generation and 110 megawatts of battery storage on about 1,500 acres within a larger 5,000‑acre area.
What’s next: The PSC will issue a final written order later this year that will specify how the approved costs translate into individual customer bills. Residents should watch for upcoming rate‑adjustment notices from We Energies as the utility incorporates the additional revenue impact into its 2027 and 2028 rate cases.
Sources: kenoshacountyeye.com