The Leander Independent School District took a decisive step on November 12 by voting 4‑2 to approve the maximum guaranteed construction costs for two new elementary schools. Trustees Sade Fashokun and Paul Gauthier voted against the limits, while Trustee Trish Bode was absent.
Budget limits and project scope
Elementary School 31 received an approved construction cost ceiling of $66.7 million, and Elementary School 32 was capped at $62.8 million. Both schools were originally authorized under Proposition A in the 2023 bond measure, which promised additional capacity for growing neighborhoods.
Location strategy and community impact
Elementary 31 is slated for the northeast portion of the district, serving the Tarvin, Parkside and Akin feeder areas. Elementary 32 will be built within the Travisso community, a location chosen after Chief Operations Officer Jeremy Trimble presented data showing that only 24% of students zoned to the current Mason Elementary live in its immediate vicinity, while 51% reside within the Travisso corridor and another 25% live in surrounding neighborhoods.
During the board meeting, more than 50 community members signed up to speak. Many parents praised the plan, noting that a new school in Travisso would make Leander ISD a more competitive choice for families. “Placing a new school facility in Travisso will go a long way toward making LISD a competitive choice for those families,” said Mason Elementary parent and Travisso resident Maggie Moore.
Opposition and enrollment concerns
Not all voices were supportive. Mason Elementary parent Jenna Edge argued that the existing Mason campus already functions as a “neighborhood school” and questioned the need for a new facility, citing demographic projections that suggest a plateau in enrollment. “Our district is at the end of the plateau; downward trend is next,” Edge said.
Trustee Fashokun, who voted against the cost limits, echoed concerns about enrollment trends, especially the impact of private and charter school options. “We’ve seen neighborhood schools end up being underenrolled to the point where we’re talking about consolidation,” she warned, adding that the district could face difficult decisions within five years.
Board rationale and timeline
Despite the dissent, the board moved forward, emphasizing the importance of staying within budget and meeting the community’s promise made in the 2023 bond. Trimble noted that both projects have already experienced schedule delays—Elementary 31 was originally expected to open in the 2025‑26 school year, and Elementary 32 in 2027‑28. He cautioned that further postponements could jeopardize the district’s ability to deliver both schools within the approved budget.
“In 2024 the traditional methods in which we approached the planning for schools was a little bit different than what we’re bringing here today,” Trimble explained. “As that growth started to slow down and that trajectory of Mason looked a little bit different, that’s when 32 planning was slowed down.”
Trustee perspectives
Trustee Gloria Gonzalez‑Dholakia defended the board’s actions, pointing out that many of LISD’s schools have been built “where kids are.” She warned that breaking bond promises could erode community trust: “When we tell our community we’re passing a bond and these are the things we’re going to do with that bond, and then we say, ‘Oh, we’re going to do a switcheroo,’ why would anyone in that community ever trust you for a bond ever again?”
Trustee Anna Smith added that the board attorney recommended a special meeting to address the cost limits before newly sworn‑in trustees could vote, ensuring procedural integrity.
Looking ahead
With the budget caps now set, the district aims to keep construction on track for both schools to open by the 2028‑29 school year. The board’s decision reflects a commitment to delivering on bond promises while balancing fiscal responsibility and community input.