In a September 21 letter, Governor Greg Abbott directed the Texas Commission on Environmental Quality (TCEQ) to halt every new permit for data‑center projects until the Electric Reliability Council of Texas (ERCOT) completes its audit of proposed facilities. The move comes as the governor seeks to ensure that booming data‑center development does not strain Texas’ water resources or electric grid.
Audit to cover tax breaks, water use and community impact
ERCOT’s audit, expected to finish by the end of the year, will examine the tax exemptions data centers receive, their projected water and electricity consumption, how they plan to limit disturbances to local neighborhoods, and the ownership structures of each proposed site. Governor Abbott said the process will give TCEQ “sufficient information, including information gained from pending audits, and time to thoroughly review all proposed permits to make fully informed permitting decisions.”
Water‑use data collection enforced
Earlier in September, Abbott instructed the Texas Water Development Board (TWDB) to work with ERCOT to collect “critical water use information” from data‑center operators. The TWDB had already sent a mandatory survey to more than 300 facilities; as of September 1, about 30% of those surveyed had responded. Abbott warned that any data‑center that fails to provide water‑usage data could be reported to local law enforcement.
Local officials and advocates welcome the pause
Luke Metzger, executive director of the advocacy group Environment Texas, praised the governor’s order, calling it a necessary step to protect Texas’ air and water. “As Texas faces increasing pressure on our water supplies and electric grid, we need to ensure that data centers operate efficiently and sustainably,” Metzger said. He added that loopholes allowing large facilities to split gas plants and diesel generators into separate “minor” sources should be closed to protect public health.
Developers may seek work‑around options
Experts note that some developers could attempt to bypass the pause by building “behind‑the‑meter” power generation that is not connected to the ERCOT grid. However, any construction affecting at least one acre of land still requires permits from TCEQ, and industrial projects also need air permits and possibly additional approvals depending on project specifics.
Political context
The directive arrives just weeks before the November 3 election, in which Governor Abbott is seeking a fourth term. State Rep. Gina Hinojosa, a Democratic challenger, criticized the timing, urging a legislative moratorium until lawmakers can craft lasting protections for Texans. Abbott, however, reiterated his commitment to work with the legislature next year to end financial incentives for data centers and to pursue broader regulatory reforms.
Next steps
ERCOT officials plan to collect audit data through November and release a report in early December. The governor’s order remains in effect until the audit is complete and TCEQ determines that all required information has been provided.
Original reporting: Community Impact — Sugar Land — read the source article.