Milwaukee residents who rely on the 16th Street Bridge will have to wait longer for full service, as the northern segment will remain closed until June 2027, according to a statement from the Milwaukee Department of Public Works (DPW) shared with Fox 6.
The bridge, originally built in 1929, was shut down to traffic in early December 2025 after an inspection revealed a floor beam showing accelerated wear. The DPW said the damaged beam required immediate replacement, prompting the design, fabrication, and installation of a new steel replacement beam.
While the southern portion of the bridge reopened to traffic in August, it now operates with one lane in each direction to match current traffic volumes, Fox 6 reported. The reopening of that stretch between Pierce and Canal has helped restore some connectivity, but the continued closure of the northern viaduct still forces drivers onto alternate routes.
DPW officials explained that the delay stems from a greater need for replacement steel than originally anticipated during the removal and repair phases. “The longer timeframe in getting more steel materials is the main factor causing the delay,” the department said. The city and the Wisconsin Department of Transportation are actively working with the contractor to establish a revised contract completion date for the project.
Although the project team now anticipates a June 2027 reopening for the northern portion, an official update will be provided once the revised contract completion date is finalized. The DPW emphasized that the bridge’s structural integrity remains a top priority, and the additional steel will ensure the historic span meets modern safety standards.
Milwaukee commuters should continue to use the southern half of the bridge, which remains open, and plan for detours while the northern viaduct remains out of service. The city encourages drivers to stay informed about traffic changes and upcoming updates from DPW.
What’s next: The DPW will release an official update on the revised contract completion date as soon as it is set, with the goal of confirming the June 2027 reopening timeline for the northern portion of the 16th Street Bridge.