The Milwaukee Department of Public Works (DPW) announced that the northern half of the 16th Street bridge will remain closed until at least June 2027. The bridge, originally built in 1929, was slated to reopen in December 2026, but a shortage of replacement steel has forced a new timeline.
Why the Delay?
During the removal and repair phases, engineers identified a greater need for replacement steel than initially projected. The additional steel is required to replace a deteriorated floor beam that showed accelerated wear during an inspection in early December 2025. Because the bridge’s structural integrity depends on that beam, the DPW and the Wisconsin Department of Transportation are working closely with the contractor to secure the necessary materials and adjust the contract schedule.
Current Project Status
DPW officials said the project team is actively negotiating a revised contract completion date with the contractor. Once that date is finalized, an official update will be released to the public. In the meantime, the viaduct’s northern portion will stay closed to traffic, while the southern portion remains open.
Southern Portion Remains Open
The southern half of the bridge was reopened to traffic in August 2026. That segment now operates with one lane in each direction, a configuration chosen to match current traffic volumes while the northern work continues.
Impact on Commuters
Motorists who rely on the 16th Street crossing are being redirected to alternate routes, including the nearby I‑94 and the Lakefront Freeway. DPW urges drivers to plan ahead for potential congestion and to follow posted detour signage. The department also reminds residents that the bridge’s closure is a safety measure, ensuring the historic structure remains sound for future generations.
Looking Ahead
Since the bridge’s full closure in December 2025, the project team has designed, fabricated, and installed a new steel replacement beam. The additional steel required for the northern span is now being sourced, and the extended timeline reflects the realistic procurement schedule for those materials.
DPW and WisDOT remain committed to completing the project as efficiently as possible while upholding the highest safety standards. The agency will continue to provide regular updates as the revised schedule takes shape.
Community Response
Local business owners and neighborhood groups have expressed concern about the prolonged closure, noting its effect on traffic flow and nearby commerce. DPW has scheduled a public information session next month to address questions and gather feedback from affected residents.
For the latest information, motorists can visit the Milwaukee DPW website or follow the department’s social‑media channels.
Original reporting: FOX6 WITI – local news — read the source article.