Worcester officials and developers broke ground on Friday for the Colony on Grove senior‑housing redevelopment at 485 Grove Street, a project aimed at replacing outdated walk‑up apartments with modern, energy‑efficient units for older residents.
According to Hoodline, the first two phases will replace 61 pre‑Americans with Disabilities Act (ADA) walk‑up apartments with 93 new, elevator‑served homes—45 units in Phase 1 and 48 in Phase 2. The Massachusetts Housing Partnership is providing $9.65 million in permanent financing for the effort.
WB Journal reports a broader scope, stating the redevelopment will ultimately replace 139 walk‑up units with 220 modern apartments, adding 81 units overall. The project’s four‑building campus—named Apple, Birch, Cherry and Dogwood—will feature studio, one‑ and two‑bedroom units with air‑conditioning, high‑speed internet readiness, on‑site laundry, and dedicated wellness and social spaces.
Funding for the project comes from a mix of public and private sources. In addition to the $9.65 million mortgage from the Massachusetts Housing Partnership, the city has pledged $2.275 million from its Affordable Housing Trust Fund, $200,000 from Community Preservation Act funds, and $1 million in HOME program dollars, according to WB Journal. The developer, Colony Retirement Homes, also contributed capital, and the project is receiving state, federal and tax‑credit financing, including support from the Federal Home Loan Bank of Boston and M&T Bank.
Both outlets note the demographic pressure driving the need for new senior housing. The Massachusetts Housing Partnership projects a 39 percent increase in Worcester residents aged 65 and older by 2050, while 40 percent of households are already cost‑burdened. Colony Retirement Homes’ executive director Marianne Delorey said the current waitlist for affordable senior units runs about two years, with some applicants waiting up to seven years.
Construction is proceeding in phases, with each phase expected to take roughly two years. Phase 1, comprising 45 apartments, is slated for completion by early 2028, followed by Phase 2’s 48 units. The third phase will replace 24 older units with 52 income‑restricted senior apartments, and a fourth phase is estimated to contain 75 units. Residents of the existing Grove Street campus will receive a right of first refusal for the new units, and many have been observed watching the work from their lawns.
What’s next: Phase 1 is targeted for early 2028, with Phase 2 to follow shortly after. The city and developers will continue to seek additional federal funding to support the third and fourth phases, expanding senior‑housing inventory across Worcester.