Gov. Tony Evers has signed a $6.87 million contract to improve seven flyover ramps in Northeast Wisconsin. The project includes six ramps on I-41 in Brown County and one ramp in Winnebago County.
Project Details
Work on the six Green Bay structures is set to begin on July 7 and is expected to finish this year. The Winnebago County ramp work is scheduled for 2027. The improvements will include milling a portion of the deck, performing deck repairs, and overlaying with a polyester polymer concrete (PPC) overlay.
During the construction, two-lane ramps will remain open during the day with lane closures, and single-lane ramps will be closed and detoured. There may be temporary evening and overnight full closures for repair work. Lane closures may cause delays during peak travel times.