Trumbull Council Approves AI Upgrade to Existing Data Center Amid Moratorium

Trumbull’s lone data center, located at 80 Merritt Boulevard, is set to be upgraded to a high‑density, AI‑ready facility. The town’s council approved the conversion on Wednesday, even as Trumbull enacted a two‑year moratorium on the establishment of new data centers.

Local officials set conditions

First Selectwoman Vicki Tesoro wrote on the town’s website that she has spoken directly with representatives from 365 Data Centers and Aphorio Carter. She said the applicants agreed to four key limits: no increase in electrical draw beyond the existing site capacity, no increase in noise, no increase in water use, and no expansion of the building’s footprint.

“I told the applicant directly: no increase in electrical draw beyond existing site capacity, no increase in noise, no increase in water use, no expansion of the building’s footprint. They have agreed to all four,” Tesoro wrote.

Expert concerns about power and water use

Kenneth Gillingham, a professor of environmental and energy economics at the Yale School of the Environment, cautioned that AI‑ready facilities consume more power and water than traditional data centers. “This is going to be a small data center that probably will use more electricity than the previous one did,” Gillingham said. “That puts added pressure on our grid, especially during peak times.”

He added that Connecticut’s electricity rates are already high. “Our electricity rates are certainly high enough right now. And so, it would continue to exacerbate our high electricity rates,” Gillingham noted. “It’s not going to change anything immediately, but it provides pressure so that Eversource and UI are going to come back and have to pay higher supply rates. They’re going to have to pass on some of those costs to the consumers.”

Moratorium does not block the upgrade

The town’s moratorium applies only to the “establishment and development” of brand‑new data centers. It does not restrict upgrades to the existing facility, a point raised by resident Sherry Boyd, who said, “We have two years to learn and protect ourselves from what else might come, but it doesn’t protect us from what’s happening right now.”

Other Connecticut communities have adopted similar restrictions. Morris passed a two‑year moratorium in May, while Groton and West Haven enacted one‑year moratoriums.

Residents voice skepticism

Some Trumbull residents remain uneasy. Sarah Beck expressed concern that the town council has not asked enough questions. “We don’t feel that there have been enough questions asked, not enough information gathered. And because these technologies are so new, it’s hard to know what we don’t know about these data centers,” she said.

Richard White suggested a petition‑driven referendum as a possible check on future expansion. He estimated that roughly 2,400 signatures would be needed to trigger a vote, noting, “If we pull that off, then the town council has a choice: they can either accept our changes or we can have a referendum and the town can vote on it. And I suspect we would win.”

Potential future expansion

The current facility operates at about 15 megawatts, roughly the power usage of three large hospitals. Gillingham warned that the data center owner has “every incentive to expand.” He projected that, if AI data center growth continues nationwide, the operator may request increases to 20 or even 30 megawatts, putting further strain on the local grid.

Connecticut Public requested a copy of 365 Data Centers’ letter of intent for the Trumbull site. The company declined, citing confidentiality and the non‑binding nature of the document, and indicated no timeline for future public announcements.

What’s next?

The council will need to develop enforcement mechanisms for the agreed‑upon limits, and residents plan to monitor the facility’s performance closely. The outcome will likely shape how other Connecticut towns balance emerging AI infrastructure with community and environmental concerns.


Original reporting: The Connecticut Mirror — read the source article.

OBBM Network Editorial Staff

[email protected]

Editorial team behind OBBM Network — independent, hyper-local journalism syndicated through HyperLocalLoop and OBBM Network TV.

Leave a Reply

Your email address will not be published. Required fields are marked *

Recent News

Trending

Community News

Quick Start Deal

Turn Local Reach Into Real Leads

A monthly bundle that puts your business in front of local audiences across HyperLocal Loop and the OBBM Network — and delivers ready-to-contact buyers to your team.

$500 Per Month
What's Included
  • LeadEngine · 1,000 Contacts Verified, buyer-intent prospects in your market, delivered to your team
  • DataPulse · 1,000 Matches Identify and retarget anonymous visitors to your site
  • Banner Ads · 3 Cities Geo-targeted display placement across HyperLocal Loop in three cities
  • Video Commercial · 3 Cities Your commercial airs on the local OBBM channel in three cities
  • Audio · 10,000 Impressions Podcast ad impressions across the OBBM Network
  • Geo-Targeting City or regional targeting via AdServe
  • Real-Time Reporting Track campaign performance as it happens
Questions about any of this? Ask Ben →
Get Started
Secure checkout · Cancel anytime
Quick Start Deal

Get Loop-Ready in One Move

A low-commitment monthly bundle that keeps your business in front of local audiences across HyperLocal Loop and the OBBM Network.

$350 Per Month
What's Included
  • DataPulse · 1,000 Matches Identify and retarget anonymous visitors to your site
  • Banner Ads Geo-targeted display placement across HyperLocal Loop
  • Video Ad Airs on your Local OBBM Channel
  • Business Advertorial A featured sponsored article telling your story
Questions about any of this? Ask Ben →
Get Started
Secure checkout · Cancel anytime
§ 04 · Choose Your Package

Three levels. Up to 60% off.

Every Patriot Package is priced at over 40% off standard AdRevv list rates — and the discount deepens as you scale, up to 60% off at the Enterprise tier.

Tier I · Local
The Patriot
For local & regional brands launching with the network.
List Price: $835/mo
$500/mo
★ Save $335 — 40% Off
Monthly Allotment
  • Audio: 10,000Podcast impressions
  • Video: 10,000Streaming TV impressions
  • Banners: 50,000HyperLocal Loop geo-targeted banner impressions
  • DataPulse: First 1,000visitor matches included
  • City or regional geo-targeting via AdServe
  • Real-time campaign reporting
Start The Patriot
Tier III · National
The Enterprise
For national brands ready to dominate the network.
List Price: $5,065/mo
$2026/mo
★ Save $3,039 — 60% Off
Monthly Allotment
  • Audio: 14,000Podcast impressions
  • Video: 10,000Streaming TV impressions
  • Banners: 100,000HyperLocal Loop geo-targeted impressions
  • DataPulse: 5,000visitor matches included
  • LeadEngine: 20,000actionable buyer-intent contacts
  • Host Endorsements: 9podcast host-read spots
  • National geo-targeting + dedicated campaign manager
  • Priority creative production support
★ Bonus Included
Free 1-Year Freedom Chamber Membership
Faith, Family & Freedom business community at freedomchamber.net.
Start Enterprise

Need a custom configuration? Build your own package →