Rio Rancho officials announced that construction on the Springer Drive corridor will commence Monday, Aug. 24, with an anticipated completion date of Feb. 20. The project covers the stretch between Chayote Road and Santa Fe Hills Boulevard.
Scope of work
The city will replace the existing roadway and pavement structure rather than simply applying a new surface. Crews will also install new pedestrian ramps, apply fresh pavement striping, and complete related infrastructure improvements.
Project timeline and cost
A pre‑construction meeting was held on Wed., Aug. 19, after which the city confirmed a construction window that runs through Feb. 20. The city estimates the total cost at approximately $2.9 million, a figure provided by Albuquerque’s budgeting office.
Impact on drivers and residents
Motorists and nearby residents should expect typical construction activity along Springer Drive, including lane closures and temporary detours. The city advises drivers to allow extra travel time and to follow posted signage.
Community context
Springer Drive is a key corridor for daily commuters and local businesses. The upgrades aim to improve safety for both drivers and pedestrians, reflecting Rio Rancho’s ongoing commitment to maintaining reliable transportation infrastructure.
City officials will continue to provide updates as the project progresses. Residents can monitor the city’s website or contact the public works department for the latest information.