Rapid City, South Dakota – In a decisive meeting on November 26, the Rapid City Planning Commission voted against Mayor Jason Salamun’s request for a six‑month moratorium on new data‑center applications. Instead, commissioners backed an alternative ordinance that strengthens existing protections while still allowing approved projects to proceed.
Commission’s Reasoning
Commission members said the revised ordinance strikes a balance between industry growth and community well‑being. Planning Manager Jessica Olson explained that staff is “balancing the priorities of industry with our neighborhoods, making sure they’re compatible, or if they’re not, that they’re distanced or have other precautions in place so they’re not negatively impacted.”
Mayor’s Perspective
Mayor Salamun, who advocated for the pause to give the city time to finalize a permanent set of regulations (Ordinance 6746), praised the commission’s decision as a step forward. “This is a hot topic all around the country, and trying to apply logic and reason and say, okay, let’s protect water, let’s protect our power, let’s protect our neighborhoods—that’s what it’s all about,” he said. “I think today we took a good step getting there. I think there’s still work to do, but there you go.”
Impact on Ongoing Projects
The alternative ordinance does not halt the permitting process for a 49.9‑megawatt data center currently being developed by Dream Design. The developer has supported the updated ordinance, preferring it to a full pause that could delay construction and investment.
Public Concerns
Approximately 940 Rapid City residents have voiced concerns in recent weeks about the potential impacts of data‑center development, citing water usage, noise, rising energy costs, and sewer impacts. The commission’s recommendation will now move to the city’s Legal and Finance Committee before reaching the full City Council for a final vote.
Next Steps
City Council is scheduled to consider the ordinance on January 21, 2027. Residents will have multiple opportunities to comment before a final decision is made, ensuring that community input remains a central part of the process.
For more information on upcoming public comment periods or to submit feedback, residents are encouraged to visit the city’s official website or contact the Planning Department directly.
Original reporting: KOTA (Gray) – local — read the source article.