Rapid City, S.D. – Pennington County officials are moving forward with the review of a proposed 20‑megawatt modular data center that would be built near Old Folsom Road. The project, submitted by Nodiac Development LLC, is currently under a conditional use permit process that the Planning Commission extended through Jan. 25, 2027.
Extensive groundwork before approval
County staff spent roughly a year researching data‑center operations before adopting a set of regulations in 2025. Those rules address common community concerns such as noise, water consumption, electricity demand, setbacks, storm‑water management and road access. Planning and Zoning Director Brittney Hand said the regulations are meant to mitigate potential impacts while still allowing responsible development.
Key questions remain
Residents have asked how much electricity and water the facility will require and whether noise could affect nearby properties. The county has indicated that the developer will be responsible for any necessary electrical infrastructure upgrades. Black Hills Electric Cooperative has issued a conditional “will‑serve” letter, but additional studies are needed to confirm that sufficient power is available.
The developer proposes a closed‑loop cooling system that would initially need about 28,000 to 30,000 gallons of coolant. The system would recirculate the coolant and replace it every five to eight years. No new well or direct water connection is planned, although the source of the initial water supply has not yet been confirmed.
Noise and site‑specific studies
County staff have also requested a detailed noise study that would examine equipment sounds, low‑frequency noise and vibration. Hand emphasized that the permit process allows the county to request additional information and impose conditions tailored to the specific site.
Next steps in the permitting timeline
The Planning Commission voted to continue its review until Jan. 25, 2027, giving Nodiac Development time to satisfy outstanding property platting requirements. Further technical studies and infrastructure reviews are still pending before the commission can issue a final decision.
Pennington County’s methodical approach reflects a commitment to balanced growth: protecting community quality of life while encouraging modern, responsible technology infrastructure that can support local businesses and jobs.
Original reporting: KOTA (Gray) – local — read the source article.