Crews have started building the foundation for the new Roosevelt Bridge on U.S. 70 over Lake Texoma, a development that matters to Sherman drivers who rely on the crossing for daily travel and commerce.
According to ODOT spokesperson T.J. Gerlach, the first drilled shaft – a large concrete pillar driven down to bedrock – was poured last week on land. “Last week we poured the first, what’s called drilled shaft. Kind of forms the foundation of the future piers for the new bridge,” Gerlach told KXII.
ODOT plans to install about 125 drilled shafts in total, most of which will be placed in the water. After each shaft is completed, barges and drilling equipment will be moved to the next location, with Gerlach estimating a new shaft will be poured every two to three days, weather permitting.
The bridge project, which began construction in September, remains on schedule. “This is a big long project, but you know, so far things are progressing very smoothly. We’re pretty much on track for where we are right now, but you know, it’s still early days,” Gerlach said.
Drivers crossing the Roosevelt Bridge this holiday season should expect increased activity on the water as crews continue foundation work. The three‑year construction timeline projects completion around 2029, promising a modern, more stable crossing that will benefit commuters, freight operators, and local businesses in Sherman and the surrounding region.
What’s next: ODOT will continue pouring drilled shafts at the projected pace, moving barges and equipment as each pillar is completed. Residents can look forward to ongoing updates as the bridge moves toward its anticipated 2029 opening.
Sources: kxii.com