Blue Origin disclosed a major $3 billion investment to broaden its manufacturing, payload processing and launch infrastructure throughout Florida. The expansion is aimed at enabling the company to conduct several New Glenn missions each week by the end of the decade, a milestone that promises new jobs and economic growth for the Space Coast.
Expanded footprint and new capabilities
Today the aerospace firm operates more than 20 sites across Brevard and Orange counties, employing over 5,000 workers and partnering with 500 suppliers in the state. The new investment will add a $330 million expansion at Rocket Park, the 1.37‑million‑square‑foot campus near NASA’s Kennedy Space Center, to build New Glenn’s 9×4 second‑stage upper sections. Once completed in summer 2027, the facility is designed to produce up to 150 upper stages each year.
Additional automation—including machining, welding, material handling and inspection equipment—will speed production and allow the company to prepare multiple missions simultaneously. Blue Origin also plans to increase in‑house manufacturing of components, systems and products while maintaining relationships with outside suppliers.
New customer integration and launch facilities
In partnership with the U.S. Space Force, Blue Origin is constructing a customer integration facility at Cape Canaveral Space Force Station. The building will feature four payload bays, two encapsulation bays and a dedicated multimanifest processing area to support New Glenn 7×2 and 9×4 vehicles, including those assigned to national‑security missions.
A separate vertical‑integration facility will enable parallel vehicle and payload preparation, further increasing launch cadence. The company is also upgrading Launch Complex 36 (LC‑36) at Cape Canaveral. LC‑36A, the first newly rebuilt launch complex at the site since the 1960s, is being restored after an anomaly earlier this year, while LC‑36B is under construction and slated to become the primary launch pad for New Glenn 9×4.
Blue Origin has filed an environmental assessment to raise the permitted launch rate at LC‑36 from 12 to 50 launches per year, reflecting its ambition for frequent, reliable access to space.
Additional launch pads and booster recovery
The company intends to build extra New Glenn launch pads on the Space Coast to supplement the two at LC‑36, providing redundancy if a pad becomes unavailable. The design and construction approach will mirror that of LC‑36B.
Recovery infrastructure is also expanding. Port Canaveral, home to the sea‑based landing platform “Jacklyn,” will see two new platforms added to increase booster recovery capacity. A vertical‑integration facility at Cape Canaveral will process recovered first stages, inspecting and refurbishing them for future missions.
Community outreach and education
Blue Origin’s nonprofit arm, Club for the Future, reports reaching nearly 700,000 students and 65,000 educators in Florida since 2019 through STEM programming. The company’s broader Florida operations include fabrication, tooling, thermal‑protection work and development in Cocoa and Melbourne, as well as logistics and materials support in Orlando and Titusville.
These investments underscore Blue Origin’s commitment to the Florida economy, creating high‑skill jobs and reinforcing the state’s role as a hub for commercial space activity.