The Eugene City Council on Monday, Nov. 23, approved a $600,000 urban‑renewal package aimed at making downtown more pedestrian‑friendly and supporting local businesses. The plan includes replacing sidewalks on Oak Street’s west side between Sixth and Seventh avenues and converting a travel lane on each of those avenues into on‑street parking.
According to Lookout Eugene Springfield, the sidewalk and landscaping project on Oak Street will cost $350,000, while the lane‑reduction effort is estimated at $470,000. Councilors allocated $250,000 of urban‑renewal money for the lane reduction, with the remaining cost to be covered by the city’s Road Fund, which is financed primarily by the state gas tax.
The lane‑reduction pilot will shrink the four‑lane configuration on Sixth and Seventh avenues between Charnelton and High streets to three travel lanes. The right‑hand lane on each street will become on‑street parking, creating a total of 65 new parking spaces equipped with paid kiosks. Curb extensions at intersections will shorten pedestrian crossing distances, and a “buffer zone” will keep parked cars from entering the travel lane.
Transportation Planning Manager Rob Inerfeld said the change addresses long‑standing safety concerns, noting, “For years we’ve heard from people who don’t feel safe or comfortable walking back and forth across Sixth and Seventh avenues between the downtown core and the Market District.” He added that traffic models show the lane removal will not delay vehicles beyond the 20 mph speed limit that the design intends.
Councilor Eliza Kashinsky, who represents the downtown area, called the project “welcome” and said it will help the downtown feel “more connected and safer for pedestrians.” Business owners expressed mixed reactions; some welcome additional parking and a protected sidewalk, while others worry about possible congestion and parallel parking on busy streets.
In addition to the traffic changes, councilors advanced two downtown property‑improvement programs. The first program, funded with $2 million in urban‑renewal money over a five‑year pilot, will offer grants of up to $250,000 to building owners, property managers or commercial tenants for long‑term upgrades such as structural changes, new flooring, painting and seismic retrofits. The city will cover up to 70 % of project costs, with owners covering the remainder.
The second program provides up to $3,000 in grants for time‑sensitive vandalism repairs, including broken or etched windows, doors, locks, fences, gates and signs. Staff expect to open the Downtown Tenant Improvement Program for applications in the first half of 2027.
Both traffic and property‑improvement projects are slated to begin in summer 2027. The lane‑reduction pilot’s materials are designed to last about five years, and a permanent conversion would cost roughly $1 million.
What’s next: The lane‑reduction pilot will start in summer 2027, with the city monitoring traffic and pedestrian safety for five years before deciding on a permanent change. Grant applications for the Downtown Tenant Improvement Program are expected to open in the first half of 2027, giving local businesses a new avenue for funding building upgrades and vandalism repairs.
Sources: lookouteugene-springfield.com