Johnson County, Kansas – WaterOne officials are preparing for the possibility that a hyperscale data center could someday draw more than two million gallons of water a day from the county’s system. To ensure that existing residential, agricultural and small‑business customers are not burdened with higher bills, the utility’s elected board has extended a moratorium on service to extra‑large users until April.
Why the moratorium matters
Board chair Whitney Wilson explained that the pause gives the board time to study the regulatory environment and draft comprehensive rules that use the region’s water wisely. “This second moratorium gives our board time to review the regulatory environment and these projects so that any policy is comprehensive and uses our most precious natural resource wisely,” Wilson said.
Assistant General Manager Mandy Wagner added that the move is purely precautionary. “It’s preparation,” she said, noting that inquiries from a potential data‑center developer have already highlighted the need for a clear rate plan.
Proposed rate structure
WaterOne is considering a special tier – called Block 2 – for any user consuming at least two million gallons per day. Block 2 would be 50 % higher than the current Block 1 rate. For 2026, Block 1 is $5.60 per thousand gallons, while Block 2 would be $8.40 per thousand gallons.
Staff calculations show the financial impact of the higher tier. A user drawing two million gallons daily would see a monthly bill rise from roughly $336,000 under Block 1 to $504,000 under Block 2 – an annual increase of just over $2 million. At ten million gallons per day, the difference jumps to more than $10 million per year.
Protecting existing customers
Board members emphasized that the extra‑large user would be responsible for additional service charges, including pipeline, metering and infrastructure costs. Those fees are intended to keep the cost of new, high‑volume users from falling on current ratepayers.
“We want to make sure the current ratepayers are treated equitably, and that the cost would be borne by new customers and not existing ratepayers,” board member Jennifer Gunby said.
Local context and capacity
WaterOne draws water from both the Kansas and Missouri rivers, with a rated capacity of 180 million gallons per day. A two‑million‑gallon‑a‑day user would represent just over 1 % of that capacity, according to Wagner.
The utility’s largest existing customer, Coca‑Cola, typically uses between 300,000 and 400,000 gallons daily, while the sixth‑largest customer, Blue Valley School District, consumes about 80,000 gallons per day.
Future considerations
The draft regulations do not set a hard cap on water use for extra‑large users, but they would require an estimate of maximum usage in the contract, verified by a Kansas‑certified engineer. If actual consumption exceeds the estimate, an additional fee could be assessed.
Board members also noted that extra‑large users would be called upon to cut usage during a water shortage, though Wagner stressed that the focus is on equity rather than scarcity.
Political backdrop
The discussion comes as Kansas Governor‑elect Cindy Holscher, a Democrat, has proposed a moratorium on new data‑center projects during her campaign. Some board members hope to see how the next legislative session addresses data‑center water‑use policies before finalizing the utility’s own rules.
For now, WaterOne’s extended moratorium gives the board and staff the breathing room needed to craft a fair, transparent rate structure that safeguards the community while still allowing responsible development.
Original reporting: Johnson County Post (Overland Park) — read the source article.