Hallsville, Texas – On Thursday, Southwestern Electric Power Company (SWEPCO) and American Electric Power toured the newly named Hallsville Energy Hub, a repurposed site of the former H.W. Pirkey coal plant. The company announced that the project will convert the retired coal facility into a natural‑gas power plant, creating 250 construction and permanent jobs for the community.
Local economic impact
State Representative Jay Dean highlighted the importance of the development, saying, “It’s about economic development. It means new jobs.” The plant is expected to generate a steady stream of well‑paying positions, supporting families throughout Harrison County and the surrounding region.
Technical specifications
The new Hallsville Natural Gas Plant will feature two turbines and two generators, each capable of producing 225 megawatts for a combined capacity of 450 megawatts. SWEPCO claims the facility can start up in roughly 11 minutes, delivering enough electricity to power about 400,000 homes during peak demand periods.
Mark Robinson, a senior executive with SWEPCO, explained the strategic value of local generation: “SWEPCO serves three states—Arkansas, Louisiana and Texas, and while I love being able to pull electricity from those other states, I love having a local source of generation.” He added that the rapid‑start capability is crucial for emergencies and severe weather events that frequently affect East Texas.
Regulatory approval and timeline
Regulatory commissions in Texas, Arkansas, and Louisiana have each approved the Hallsville project, determining it to be in the public interest. According to the company’s press release, the plant is slated to begin serving customers in late 2027.
Broader regional benefits
Beyond power generation, the Energy Hub will house a regional distribution center, consolidating generation, operations, and logistics resources on the site. SWEPCO President and Chief Operating Officer Brett Mattison said the hub reflects the company’s long‑term commitment to East Texas: “The Hallsville Energy Hub represents our commitment to investing in East Texas while building the infrastructure needed to serve customers and communities for decades to come.”
The site is located off FM 3251 near Brandy Branch Reservoir, also known as Pirkey Lake, providing easy access for construction crews and future maintenance teams.
Community response
Local leaders and economic‑development partners expressed optimism that the project will boost the tax base, attract ancillary businesses, and reinforce Hallsville’s reputation as a growing hub for energy and industry. The plant’s quick‑start capability also offers reassurance to residents who have experienced power outages during past storms.
With the construction milestone already marked, SWEPCO and its partners are moving forward on equipment installation, site preparation, and workforce training. The company expects the plant to be fully operational and delivering reliable electricity to East Texas households by the end of 2027.
Original reporting: KLTV 7 Tyler (news) — read the source article.