At a November 23 public‑works meeting, Plano’s community‑investment program manager Drew Zaeske presented results from the city’s nighttime construction pilot. The initiative, which targets arterial roadways and major intersections in commercial and industrial zones, aims to replace concrete panels without full lane closures and to limit noise and disruption for nearby residents.
Pilot sites and parameters
The pilot included two locations: a concrete‑replacement project on Custer Road and Legacy Drive, and a larger zone along Park Boulevard between Preston Road and Ohio Drive. Both sites were chosen because they meet three criteria: they are on major thoroughfares, they serve commercial or industrial areas, and they maintain a 500‑foot buffer from residential properties. Work was limited to 9 p.m. – 5 a.m., using fast‑setting concrete that allows traffic to resume the next morning.
Speed gains and traffic flow
Zaeske reported that the first site, a relatively small panel replacement, was completed in four days. Public‑works estimates suggest the same work would have taken two weeks if performed during daylight hours. The second, larger zone required eight weeks, which is roughly comparable to a daytime schedule, but the city kept two lanes open throughout the day, preserving traffic flow.
City Manager Mark Israelson emphasized the benefit to commuters and businesses: “The level of disruption, when you talk about the driveways, minimizing that impacts local businesses. We think that if we’re able to do this in a way that is more efficient and it has less disruption to daily commutes, businesses and things of that nature, that is maybe a non‑financial benefit, but one nonetheless.”
Safety and community feedback
Resident complaints about noise were tracked, and the department recorded one accident at each site, both attributed to inattentive drivers rather than construction activity. Overall, the pilot demonstrated that nighttime work can be performed safely while maintaining open lanes for daytime traffic.
Looking ahead
Plano completed concrete repairs on Communications Parkway, McDermott Road, Custer Road, and Coit Road in 2026. Sections of those streets and a portion of Alma Drive are slated for nighttime asphalt overlays in 2027, with overlay projects scheduled through 2034. Additional concrete rehabilitation projects are planned for parts of Hedgcoxe Road, Legacy Drive, Ohio Drive, and Park Boulevard in 2027.
The city’s broader nighttime construction program dates back to 2021, when asphalt overlays began to be applied after dark. The current method includes an emulsion layer over newly replaced concrete before the fast‑setting asphalt is laid, a technique expected to extend pavement life for 15 years before the next major replacement.
Community impact
By reducing the overall time that roadways are under construction, Plano aims to lessen congestion, protect local businesses from prolonged driveway closures, and provide a smoother commuting experience for residents. The pilot’s success supports the city’s continued use of nighttime construction as a tool for efficient infrastructure maintenance.