Lake Texoma, Oklahoma – The Oklahoma Department of Transportation (ODOT) announced that the long‑awaited replacement of the Roosevelt Bridge on U.S. 70 is progressing smoothly. Crews have begun building the bridge’s foundation by pouring the first of roughly 125 drilled‑shaft concrete pillars.
First drilled shaft completed
“Last week we poured the first, what’s called a drilled shaft. It forms the foundation of the future piers for the new bridge,” said T.J. Gerlach, an ODOT spokesperson. The initial shaft was installed on land, but the majority of the 125 shafts will be placed in the water beneath the lake.
How the foundation is built
Each shaft starts with a large steel cage lowered by crane into a drilled hole that reaches down to solid bedrock. “It’s a big concrete pillar. We drill down to bedrock and even into it quite a bit,” Gerlach explained. Once the cage is in place, concrete is poured to create a sturdy column that will keep the bridge stable. “You don’t want bridges to move a whole lot. Your house can have a little bit of movement in it, but a bridge you really don’t want moving on the foundation itself,” he added.
Construction timeline
ODOT expects to pour a new shaft roughly every two to three days, weather permitting. “As we get one done, we’ll move the barges, move the drilling equipment over and start the next one,” Gerlach said. The project, which broke ground in September, is slated to take three years to complete. “This is a big long project, but you know, so far things are progressing very smoothly. We’re pretty much on track for where we are right now, but you know, it’s still early days,” he noted.
What drivers can expect
Motorists traveling the Roosevelt Bridge this holiday season should notice increased activity on the water as crews work on the foundation. ODOT assures the public that the construction is being managed to minimize disruption and that the bridge will remain open throughout the project.
Why the new bridge matters
The new structure will replace the aging Roosevelt Bridge, improving safety and reliability for the thousands of daily commuters who rely on U.S. 70 to cross Lake Texoma. The modern design will also accommodate future traffic growth and support regional economic development.
ODOT continues to monitor progress closely and will provide updates as the project moves forward.