LAS VEGAS — In a special session of the Nevada Gaming Control Board on Thursday, Bally’s Corp. chairman Soo Kim faced pointed questions from board chair Mike Dreitzer about the company’s promised entrance podium for the Athletics’ upcoming baseball stadium.
Board raises deadline concerns
Dreitzer, who oversees Nevada’s gaming licensing, said he has “significant concerns” that the podium – a platform on the northwest corner of the ballpark property that will connect the stadium to parking and utilities – might not be completed in time for the A’s expected arrival for the 2028 Major League Baseball season.
“From my perspective, you’re starting all these projects, and it’s your responsibility to finish all these projects in the best way you can,” Dreitzer said. “It isn’t a matter of, ‘Hey, let’s see what happens.’ Especially in the state of Nevada, that’s not acceptable.”
Bally’s response and timeline
Kim acknowledged the board’s concerns but stressed that Bally’s remains committed to the project. He noted that the podium received Clark County zoning approval in August and that construction on the stadium itself is already under way.
“We believe that each of those obligations can and will be met before April ’28,” Kim said. “There’s still plenty of time for us to build our podium that connects the corners to the stadium, as well as the shared access way that connects the podium, the utilities and the parking.”
Kim added that the company must coordinate with both the Athletics organization and Gaming & Leisure Properties, Inc., the landowner, which adds a layer of complexity to the schedule.
Regulatory oversight and next steps
Dreitzer reminded Kim that, as a Nevada gaming licensee, Bally’s must honor all contractual and regulatory commitments. “It’s on you as a licensee to make good on all of this, however you’re able to do that,” he said, noting that the board will continue to monitor progress.
The chair indicated that the podium issue will likely reappear at the board’s next meeting, expected sometime next year, and that Bally’s should be prepared to provide concrete updates on construction milestones.
Why the podium matters
The entrance platform is more than a decorative feature; it is intended to streamline fan access, improve traffic flow, and integrate utilities for the new ballpark. For a city that relies heavily on tourism and gaming revenue, the timely completion of the stadium and its supporting infrastructure is seen as a boost to the local economy and a signal of Nevada’s commitment to major sports ventures.
Local business leaders have expressed optimism that the A’s move to Las Vegas will generate jobs, increase visitor spending, and create ancillary opportunities for nearby hotels, restaurants, and retail establishments.
Looking ahead
While the board’s pressure underscores the high stakes of large‑scale development in Nevada, Kim’s assurances suggest that Bally’s believes the project remains on schedule. The next board meeting will be a key moment for the company to demonstrate tangible progress and reassure regulators that the podium will be ready for the A’s 2028 debut.
Original reporting: News 3 KSNV Las Vegas (local) — read the source article.