The City of Georgetown and Williamson County are advancing a series of road improvements that will ease traffic, add safety features, and provide new shared‑use paths for cyclists and pedestrians. These projects reflect the local government’s commitment to better infrastructure for families and commuters.
Leander Road expansion
The Leander Road corridor will be widened to four lanes from Southwest Bypass to Norwood Drive. As of September, the right‑of‑way has been fully acquired and utilities are being relocated. The Texas Department of Transportation plans to break ground on construction next October, promising a smoother flow for the growing traffic volume along this key east‑west route.
SE Inner Loop widening
A 2.91‑mile segment of the SE Inner Loop, stretching from Highway 29 to FM 1460, will be upgraded to a four‑lane, divided roadway. The project also includes a new shared‑use path for non‑motorized travelers. The city has received completed design plans and will begin advertising and bidding in November, moving the project toward the construction phase.
Ongoing improvements
- RM 2243 (Hero Way) Phase 1A: Approximately 3.5 miles between 183A and Garey Park will be reconstructed, realigned, and widened. Recent contractor work has focused on lime treatment and building shared‑use paths, according to a November 17 county commissioners update.
- Ronald Reagan Boulevard Segment D1: A new two‑lane roadway will connect RM 2238 (Williams Drive) to County Road 245. Ground was broken on October 7, and crews are currently clearing utilities and stripping topsoil in preparation for full‑scale construction.
- Williams Drive enhancements: The first phase adds a raised center median, new street lighting, landscaping, and upgraded intersections and traffic signals from Serenada Drive to Lakeway Drive. As of November, traffic control has been installed from Lakeway to Golden Oaks Drive, and milling of the center lane is set to begin. The project runs from September 2026 through late 2027, with a budget of $10.5 million funded by the city, traffic impact fees, federal grants, and tax increment financing.
- Shell Road widening: Shell Road will be expanded to four lanes with a raised median, shared‑use path, and dedicated left‑ and right‑turn lanes from Williams Drive to Sycamore Street. Crews are preparing primer and asphalt, while electrical conduit and concrete sidewalk work continue. Topsoil will be placed soon for revegetation.
Completed work
The Ronald Reagan Boulevard widening Segment B project, which added a two‑lane southbound roadway from Highway 29 to FM 3405 and converted the existing road to northbound‑only traffic, was finished about eight months ahead of schedule. County officials celebrated the early completion with a ribbon‑cutting ceremony on November 19.
These transportation updates demonstrate the collaborative effort between Georgetown and Williamson County to modernize roadways, improve safety, and support the region’s growing population. Residents can look forward to smoother commutes, more options for walking and biking, and continued investment in the community’s infrastructure.