Fulshear residents will see new park improvements as early as 2027 after the City Council gave the green light to Phase 3 of the Primrose Park project. During the Nov. 17 regular meeting, council members voted to award a $7.6 million construction contract to Crain Group LLC, a regional contractor with experience in municipal projects.
Scope of work
Matthew Riley, project manager for the city’s public works department, outlined the Phase 3 scope. In addition to standard landscaping and trail upgrades, Crain Group will enlarge the existing detention pond and convert it into an amenitized wet‑bottom pond with a neighboring sidewalk. The new pond will improve storm‑water management while providing a pleasant walking path for families.
Funding and budget details
The improvements are financed by the May 2025 voter‑approved parks bond, which allocated $10.5 million for the overall Primrose Park redevelopment. Assistant Public Works Director David Licon explained that the roughly $3 million difference between the original budget and the awarded contract will be redirected toward additional amenities, including an expanded amphitheater, upgraded audio‑visual equipment, a second restroom facility, and the purchase of an aerator to keep the pond water healthy.
“Now we can do some of the more fun things that I think the city would like to see in a park that we’ve invested so much in,” Licon said, emphasizing the community‑focused nature of the enhancements.
Phase 2 recap and upcoming timeline
Phase 2 of the Primrose Park project, completed earlier this year, added four baseball and softball fields, sports lighting for all fields, a combined restroom and concession building, and required parking and detention facilities. The city celebrated the opening of Phase 2 with a ceremonial first pitch on June 13.
Construction on Phase 3 is scheduled to begin in December and is expected to take nine months, putting the park’s new features in place by the fall of 2027. Residents can look forward to a more versatile recreation space that supports both active play and passive enjoyment.
Community impact
The expanded park aligns with Fulshear’s long‑term vision of providing high‑quality, family‑friendly amenities that strengthen neighborhood ties. By investing bond dollars into tangible improvements, the city demonstrates its commitment to preserving open space while meeting the growing needs of a fast‑expanding community.
Local families, youth sports leagues, and senior groups have all expressed enthusiasm for the upcoming upgrades, noting that the enhanced pond and sidewalk will create new opportunities for walking, fishing, and outdoor gatherings.
Next steps
City officials will continue to provide updates through public meetings and the city’s website. Residents interested in learning more about the project timeline or providing feedback can contact the public works department or attend the next council session.