Friendswood Independent School District used its November 16 board of trustees workshop to lay out a slate of facility improvements funded by the district’s 2026 bond program. The plan focuses on priority maintenance, classroom enhancements and upgrades that directly benefit students and staff across the community.
Bond funding breakdown
The 2026 bond allocates $25 million for district‑wide priority maintenance. Chief Financial Officer Amber Petree explained that roughly $1.8 million of that amount is earmarked for new school buses, leaving about $23 million for other infrastructure projects.
In addition, the district still has approximately $4 million remaining from its 2020 bond, designated for critical infrastructure work, and nearly $2.2 million available through the capital projects fund for campus‑level improvements not covered by the 2026 bond.
Classroom and science upgrades
Science labs at Bales Intermediate and Windsong Elementary will be renovated. Existing classrooms will be converted into dedicated science learning spaces with added instructional and storage areas, laboratory sinks and magnetic writable wall surfaces, giving students modern, hands‑on learning environments.
Maintenance and safety projects
Friendswood Junior High will see erosion repairs beneath sidewalks and a sloping correction in its band room. Friendswood High School’s plan includes bathroom renovations, flooring replacements and a full replacement of the school’s main waterline. The district also intends to replace the roof on the administration building, ensuring long‑term protection for district offices.
New athletic and playground amenities
Working with campus leadership, the board identified several capital projects. At Westwood Elementary, the library will be redesigned after mold damage required the removal of many materials. The district is also exploring an upgrade to the pre‑kindergarten playground behind the gym, adding swing sets and ADA‑compliant inclusive equipment for younger students.
Friendswood High School will expand athletic locker space by reconfiguring existing facilities, providing lockers for athletes while their sports are in season. Additional improvements include HVAC and mechanical upgrades, fire alarm system updates and security enhancements.
Geotechnical study postponed
The board tabled a nearly $175,000 request for geotechnical engineering services for the career and agricultural sciences center, opting to seek more affordable options. The proposed work would have included a geological fault study, soil borings, groundwater measurements and laboratory testing.
Next steps
District officials will continue to evaluate project scopes, costs and funding options before presenting final recommendations to the board. The transparent process reflects the district’s commitment to responsible stewardship of taxpayer dollars while delivering needed improvements for students, teachers and families.
Original reporting: Community Impact — Houston — read the source article.