At a City Council work session on November 9, Eugene officials unanimously approved a request for $91 million in Oregon lottery‑backed bonds to help fund a third concourse at the city‑owned airport. The expansion, estimated at $450 million, would add eight new gates and is projected to increase the airport’s annual regional economic impact.
Economic‑impact figures under review
Airport Director Cathryn Stephens previously told councilors that the new concourse could more than double the airport’s impact, from $1.6 billion to $3.6 billion. An investigation by Lookout Eugene‑Springfield found that the $3.6 billion figure was calculated by adding overlapping measures – business revenue, personal income and tax impacts – that should not be summed together.
Martin Associates, the consulting firm that produced the 2024 impact study, warned that personal income is already included in business revenue, and that tax revenues overlap with those figures. University of Oregon economics professor Bruce Blonigen confirmed the double‑counting, noting that adding projected state and local taxes to personal income inflates the total.
Airport’s response and next steps
In a statement to Lookout on November 16, Stephens acknowledged the overlap and said the airport has re‑engaged Martin Associates to revise the forecast. She indicated a corrected impact number will be released “in the coming weeks.” The firm has been providing clarification within the original scope of work at no additional charge.
While the disputed $3.6 billion figure has been removed from the airport’s liftoffeug.com website, the agency continues to promote the expansion’s benefits. Stephens emphasized that the economic growth stems directly from building the third concourse.
Funding request and legislative outlook
The $91 million request would consume nearly a quarter of the $400 million lottery‑bond capacity allocated for the 2027‑29 biennium. If state lawmakers approve the funding next year, the airport will move forward with the two‑phase expansion plan.
Local business group Turell Group, which prepared a feasibility study for the airport, also warned against adding overlapping economic measures. Their 54‑page report echoed Martin Associates’ caution that the impacts are separate and not additive.
Community perspective
Despite the technical dispute over the impact numbers, several local experts see the expansion as a needed upgrade. Blonigen noted that the airport is experiencing “pretty crazy packed” traffic and that the additional gates would improve capacity for the five‑county region.
City Council members have expressed confidence that the project will create construction jobs and long‑term employment opportunities, aligning with Eugene’s broader economic development goals.
What’s next?
Stakeholders will await the revised economic‑impact estimate before the state funding request moves forward in the 2027 legislative session. The airport plans to release the updated figures in the coming weeks, providing a clearer picture of the projected benefits for the region.