DISD approves $5.37 million budget increase to expand Ginnings Elementary into PK‑8 academy

Denton Independent School District (DISD) trustees voted on Nov. 10 to begin converting Ginnings Elementary School from a pre‑kindergarten‑to‑fifth‑grade campus into a pre‑kindergarten‑to‑eighth‑grade academy. The decision matters to Denton families because it expands local school options and alters the district’s construction schedule and budget.

According to Community Impact, the board approved a $5.37 million increase to the district’s general contract for additional facilities. The increase consists of a $4.91 million rise in the construction guaranteed maximum price and $457,038 for added design fees and testing soft costs. Those changes lift the project’s total probable cost from $63.28 million to $68.65 million.

The expanded educational model required revisions to the architectural plan prepared by Corgan Associates Inc. The updated design adds an activity room adjacent to the gymnasium, dedicated middle‑school dressing rooms, a second science laboratory, a second art classroom, and a fine‑arts multipurpose room. Campus finishes and branding will also be adjusted to suit a broader age span of students.

Ginnings Elementary was temporarily closed ahead of the 2025‑26 school year to rebuild the campus under the district’s voter‑approved 2023 bond package of more than $1.4 billion. The original rebuild plan called for a pre‑K‑to‑fifth‑grade school, the same configuration used before the closure. While construction proceeds, students from Ginnings have been rezoned to nearby Evers Park, Hodge, and Schulz elementary schools.

The budget adjustment also extends the construction timeline by 155 days. DISD documents now list the revised date of substantial completion for the Ginnings PK‑8 campus as Oct. 26, 2027, later than the previously scheduled spring 2027 finish. The district has not provided a new opening date for the school.

What’s next: DISD will continue monitoring the construction schedule and will likely update the community on the opening timeline as the Oct. 26, 2027 substantial completion date approaches. Residents can watch future board meetings for additional budget or timeline adjustments.


Sources: communityimpact.com

OBBM Network Editorial Staff

[email protected]

Editorial team behind OBBM Network — independent, hyper-local journalism syndicated through HyperLocalLoop and OBBM Network TV.

Leave a Reply

Your email address will not be published. Required fields are marked *

Recent News

Trending

Community News

Quick Start Deal

Turn Local Reach Into Real Leads

A monthly bundle that puts your business in front of local audiences across HyperLocal Loop and the OBBM Network — and delivers ready-to-contact buyers to your team.

$500 Per Month
What's Included
  • LeadEngine · 1,000 Contacts Verified, buyer-intent prospects in your market, delivered to your team
  • DataPulse · 1,000 Matches Identify and retarget anonymous visitors to your site
  • Banner Ads · 3 Cities Geo-targeted display placement across HyperLocal Loop in three cities
  • Video Commercial · 3 Cities Your commercial airs on the local OBBM channel in three cities
  • Audio · 10,000 Impressions Podcast ad impressions across the OBBM Network
  • Geo-Targeting City or regional targeting via AdServe
  • Real-Time Reporting Track campaign performance as it happens
Questions about any of this? Ask Ben →
Get Started
Secure checkout · Cancel anytime
Quick Start Deal

Get Loop-Ready in One Move

A low-commitment monthly bundle that keeps your business in front of local audiences across HyperLocal Loop and the OBBM Network.

$350 Per Month
What's Included
  • DataPulse · 1,000 Matches Identify and retarget anonymous visitors to your site
  • Banner Ads Geo-targeted display placement across HyperLocal Loop
  • Video Ad Airs on your Local OBBM Channel
  • Business Advertorial A featured sponsored article telling your story
Questions about any of this? Ask Ben →
Get Started
Secure checkout · Cancel anytime
§ 04 · Choose Your Package

Three levels. Up to 60% off.

Every Patriot Package is priced at over 40% off standard AdRevv list rates — and the discount deepens as you scale, up to 60% off at the Enterprise tier.

Tier I · Local
The Patriot
For local & regional brands launching with the network.
List Price: $835/mo
$500/mo
★ Save $335 — 40% Off
Monthly Allotment
  • Audio: 10,000Podcast impressions
  • Video: 10,000Streaming TV impressions
  • Banners: 50,000HyperLocal Loop geo-targeted banner impressions
  • DataPulse: First 1,000visitor matches included
  • City or regional geo-targeting via AdServe
  • Real-time campaign reporting
Start The Patriot
Tier III · National
The Enterprise
For national brands ready to dominate the network.
List Price: $5,065/mo
$2026/mo
★ Save $3,039 — 60% Off
Monthly Allotment
  • Audio: 14,000Podcast impressions
  • Video: 10,000Streaming TV impressions
  • Banners: 100,000HyperLocal Loop geo-targeted impressions
  • DataPulse: 5,000visitor matches included
  • LeadEngine: 20,000actionable buyer-intent contacts
  • Host Endorsements: 9podcast host-read spots
  • National geo-targeting + dedicated campaign manager
  • Priority creative production support
★ Bonus Included ★
Free 1-Year Freedom Chamber Membership
Faith, Family & Freedom business community at freedomchamber.net.
Start Enterprise

Need a custom configuration? Build your own package →