The village of Bristol’s plan commission voted to table the conditional use permit for a proposed solar farm on roughly 380 acres of agricultural land, pushing the decision to its next meeting on Dec. 22. The project, led by US Solar, would generate enough renewable electricity to serve an estimated 10,000 to 12,000 homes, according to the developer.
According to Urban Milwaukee, the commission’s Tuesday night meeting highlighted resident concerns about the removal of approximately 334 mature oak trees and the potential for increased stormwater runoff affecting nearby George Lake. Village trustee Chris Leker, who also serves on the plan commission, said the board wants additional time to understand the project’s impacts. “We take the concerns of the citizens very seriously, and we’re trying to address them as best we can while also preserving property rights of landowners,” Leker told the commission.
Local resident Ross Castona, who lives adjacent to the proposed site, expressed mixed feelings. While he worries about water collecting on his property, he remains supportive of alternative energy sources, noting, “I don’t know why they couldn’t be put on rooftops and parking lots, and leave the land for crops or raising cattle.”
Another neighbor, Priscilla Kopczynski, objected to the planned removal of the oak trees, stating, “They are beautiful old oak trees… I don’t see what’s green about removing a tree, which gives us the oxygen we need to breathe.” In response, project development director Peter Schmitt said US Solar will replace the trees with larger specimens and install pollinator habitat to improve water and soil quality. He added that converting the land from seasonal corn and soy to perennial deep‑rooted vegetation would help naturally purify water and reduce runoff.
Village President Mike Farrell emphasized the board’s commitment to a thorough evaluation, saying, “Our village board and staff are deeply committed to a thorough evaluation of the pros and cons for this project.” The commission’s decision to delay reflects a desire to balance renewable energy benefits with local environmental and property concerns.
What’s next: The Bristol plan commission will reconvene on Dec. 22 to revisit the conditional use permit. Residents and stakeholders are encouraged to attend the meeting to voice additional input before a final decision is made.
Sources: urbanmilwaukee.com