The Alabama Department of Transportation (ALDOT) released a detailed schedule of upcoming construction milestones for the I‑10 Mobile River Bridge and Bayway project, a major infrastructure effort that will reshape traffic flow across the Mobile River.
Foundations and East Approach Begin
In October 2026, crews began foundation work for the bridge towers on both the east and west sides of the Mobile River. This early phase sets the stage for the six‑lane cable‑stayed bridge that will replace the aging structure currently serving I‑10 traffic.
Following the foundation work, construction of the east approach bridge started in November 2026. The east approach will link the new cable‑stayed span to the existing Bayway on the river’s eastern bank, providing a seamless connection for motorists heading toward downtown Mobile.
West Approach Planned for Early 2027
ALDOT announced that work on the west approach bridge is scheduled to begin in January 2027. This segment will tie the new bridge into the existing I‑10 corridor on the river’s western side, completing the primary connections needed for the project’s full operation.
Future Phases and Project Timeline
After the approach bridges are in place, the project will move into several major phases, including the erection of the east and west bridge towers, construction of the main‑span superstructure, installation of stay cables, and final completion of the main spans. Detailed schedules for these later stages will be released as work progresses.
ALDOT emphasized that construction schedules remain subject to change due to weather, site conditions, and other factors. The agency pledged to keep the public informed about lane closures, traffic impacts, and any adjustments to the timeline.
Community Impact and Expectations
Local residents and commuters can expect temporary disruptions as the project advances, but the long‑term benefits include a modern, higher‑capacity bridge that will improve safety and reduce congestion on one of the region’s most heavily traveled corridors. The new bridge is designed to accommodate future traffic growth and support economic development throughout Mobile and the surrounding Gulf Coast area.
ALDOT projects that the entire Mobile River Bridge and Bayway project will be completed by October 2031. Ongoing updates, including lane‑closure notices and traffic‑management plans, will be posted on the ALDOT website under the “Mobile River Bridge & Bayway” news section.
Looking Ahead
The initiative reflects Alabama’s broader commitment to investing in critical infrastructure that supports families, businesses, and the freedom of movement for all citizens. By modernizing this key transportation link, the state aims to strengthen the region’s economic vitality while preserving the safety and convenience of daily commuters.