Raleigh residents should watch a pending decision in nearby Selma that could influence the state’s electricity landscape. On Monday evening, the Selma planning board is set to review a conditional rezoning request and special‑use permit for Montana‑based Advanced Manufacturing, Inc.’s proposed 177,000‑square‑foot, single‑story facility known as “Project Volt,” according to WRAL.
The developer’s application covers more than 100 acres near I‑42 and Buffalo Road. Residents living close to the site, including fourth‑generation homeowner Ron Parrish, say they are contemplating selling their homes if the project proceeds. “There’s no way you can tell me I’m not going to be able to hear that thing around the clock if I decide to stay,” Parrish told WRAL. He added that neighbors have already discussed potential property sales with the developers.
Community concerns focus on water consumption, electricity use, and noise. At recent public meetings, attendees called for greater transparency from town officials. “For a while, it’s going to hurt. What that’s going to bring, we just don’t know and that’s what’s causing a lot of headache here,” Parrish said.
Selma leaders approved new data‑center regulations last month that address electricity, water usage, cooling and noise levels. The town staff report notes that many ordinance items will not be required until a building design is completed, and that an approved electricity study must be finished before construction can begin. Mayor Byron McAllister indicated a council vote could occur early next month, though he did not comment on resident worries.
State‑wide, the North Carolina Utilities Commission has just adopted stricter financial safeguards for data‑center developers, a move that could affect Project Volt’s economics. The commission’s order, reported by WRAL, requires qualifying data centers to sign electricity service contracts of at least ten years, pay demand charges on a minimum of 75% of their contracted capacity, and provide upfront funding for dedicated infrastructure and transmission upgrades.
Governor Josh Stein praised the protections, saying they help ensure data centers “pay for some of their costs” and protect consumers. “While the orders on large‑load tariffs provide multiple important consumer protections … it is far from the end of our work,” Stein said.
Utilities Commissioner Floyd McKissick warned that without such safeguards, households could be left footing the bill for billions of dollars in grid investments if a data center closes early. He estimated roughly 20 previously signed agreements would have escaped the new requirements.
Industry voices noted the rules go beyond existing Duke Energy contracts. Duke spokesperson Bill Norton said the utility has not heard developers plan to abandon projects because of the new requirements. Dan Diorio of the Data Center Coalition argued that singling out data centers does not protect residents from other large‑load users, while coalition director Alex Cutchey emphasized that cost allocation should reflect a customer’s impact on the system.
Both the Selma board’s upcoming decision and the state’s new utility rules have direct implications for Raleigh’s power bills and local development patterns. Residents can expect further discussion at the Selma council meeting slated for early next month, and the Utilities Commission will monitor compliance as projects move forward.
What’s next: The Selma planning board will vote on the rezoning and special‑use permit Monday night, with a town‑council vote likely early next month. Meanwhile, the Utilities Commission will begin enforcing the new financial safeguards for data‑center projects that begin service after the rule’s effective date.