At a public meeting held Tuesday night in the Canyon County Fairgrounds, Caldwell residents and business owners gathered to review proposed changes to the congested intersection of Linden Street and Cleveland Boulevard. The open‑house format allowed neighbors to see design mock‑ups from DKS Associates, the engineering firm hired by the city, and to ask questions of project managers.
Community concerns and personal stories
Long‑time resident Tina Baney recounted a serious crash she witnessed about two and a half years ago involving an intoxicated driver with children in the back seat just down the block from the intersection. “It scared me so much I couldn’t go on and care for the man I was supposed to care for that day,” Baney said, emphasizing the personal impact of traffic safety in the area.
Neighbors also expressed frustration over past construction projects that they felt left the city’s main thoroughfares disrupted and communication lacking. Despite these worries, many agreed that the current layout is “crowded, inconvenient and sometimes downright dangerous.”
Data driving the redesign
The City of Caldwell reports that between 2019 and 2023, 50 crashes occurred near the Linden‑Cleveland intersection, 23 of which resulted in injuries. City officials anticipate continued traffic growth along Cleveland Boulevard as Caldwell expands.
In response, the city’s preliminary plan includes:
- New right‑turn lanes on Linden Street to separate turning traffic from through traffic.
- A center left‑turn lane to improve flow for vehicles heading east on Cleveland Boulevard.
- An upgraded traffic signal with flashing pedestrian phases.
- Median installations and additional pedestrian safety measures.
- Conversion of certain business entrances to right‑in/right‑out access to reduce conflict points.
City traffic engineers project that these improvements could reduce the average evening rush‑hour wait at the intersection from about 58 seconds to roughly 34 seconds, a potential 24‑second gain for commuters.
Resident feedback on the design
Baney expressed optimism that the right‑turn lanes could make a difference, but she cautioned that the lanes might not be long enough to accommodate the volume of vehicles entering and exiting nearby businesses. “A lot of people will still be stuck in traffic wanting to turn right because the turn lanes aren’t long enough,” she said.
Other attendees asked about the timeline. City officials indicated that design work will continue into early 2027, with construction not expected to begin until 2028. Engineers told Idaho News 6 that a cost estimate is not yet available, as the project remains in the preliminary stage.
Looking ahead
City leaders emphasized that the proposed changes aim to protect lives and improve daily travel for Caldwell’s growing population. “Our goal is to make this intersection safer for drivers, pedestrians, and our local businesses,” a city spokesperson said.
Residents are encouraged to stay engaged through the city’s Facebook group, 2C Neighborhood News, for updates on the project and future public‑input opportunities.
Original reporting: KIVI Idaho News 6 Boise metro (local) — read the source article.