The Independence City Council on Monday voted to delay a pending ordinance that would approve the assignment of a leasehold interest for a second data center in the Little Blue Valley. The council agreed to bring the resolution back for a vote on Nov. 2, giving the city more time to review the proposal.
Background on the project
Patmos, a Kansas City‑based data‑center operator that has run a facility in the former Kansas City Star Press Pavilion since May 2024, applied in June 2026 for a building permit to construct a 100‑megawatt, 285,000‑square‑foot data center at the EastGate Commerce Center, located at 2500 South Little Blue Parkway.
NorthPoint Development, which leases the industrial park from the city, currently occupies the site. The park was funded in part by Chapter 100 bonds approved by the city in May 2022 and already houses Arco business offices, the Nebius hyperscale AI data‑factory, Fort Osage School District’s Fort Connect classrooms, and the Community Services League’s EastGate Career Hub.
Lease terms and city requirements
The lease agreement gives NorthPoint the right to assign or transfer its interests in part or all of the building. Patmos seeks to acquire that space, and the deal is expected to close on Nov. 12, pending city approval. The agreement stipulates that the city may not unreasonably withhold, condition, or delay the transfer if Patmos can demonstrate sufficient experience and net‑worth to complete and operate the project.
Patmos plans to start with a 17.5‑megawatt data center on the east side of Little Blue Parkway. Because the project was approved before the city’s recent moratorium on new data‑center developments, it is grandfathered and not subject to the newly adopted zoning rules for data centers.
Community response and legal action
Residents have voiced strong opposition to the sprawling 400‑acre Nebius data‑center project approved in March 2026, and a group of Independence citizens sued Nebius, the city, and a third‑party power‑generation partner. A hearing on that lawsuit is scheduled for Oct. 22.
Critics of the Patmos proposal argue that additional large‑scale data facilities could strain local resources. Patmos counters that the new center will use fewer than 10,000 gallons of city water per day and will be equipped with six muffled backup generators, minimizing environmental impact.
What the council’s delay means
By postponing the vote, council members signal a desire for further scrutiny of the lease transfer and its implications for the community. The council’s decision aligns with the city’s recent effort to review zoning laws after the Nebius approval sparked controversy.
Mayor and council members have emphasized the importance of balancing economic development with responsible stewardship of Independence’s resources. The upcoming Nov. 2 meeting will provide an opportunity for additional public input and for the council to weigh the lease agreement against the city’s long‑term planning goals.
About Patmos
Founded in 2021, Patmos is headquartered in Kansas City, Missouri, and co‑locates with Nebius at the former KC Star printing press. The company also operates facilities in Phoenix and Dallas and has a 20‑megawatt data center under contract in Fairfield, Alabama.
Original reporting: KSHB 41 Kansas City (local) — read the source article.