Crews from El Paso Water have spent about a week lowering water levels at Cement Lake to reduce the risk of a breach. As of Monday morning, the utility had pulled nearly 20 feet of water from the reservoir, a spokesperson with EPWater said.
The drawdown began after officials identified a potential threat to the reservoir’s integrity. Workers are pumping water out and monitoring the lake closely while they assess the situation.
The effort aims to reduce pressure on the reservoir and give crews space to inspect and repair any vulnerable areas. Lowering the water level is a common step in addressing possible structural problems.
Work at the site has continued steadily through the week. EPWater crews are coordinating the removal and watching downstream conditions to limit any impacts.
Officials say they will keep the public updated as they learn more and complete repairs. Residents can expect continued activity at Cement Lake until the risk is fully addressed.