While most of New York City sleeps, a dedicated crew from American Christmas works through the night to transform the city into a holiday wonderland. CEO Dan Casterella says the company typically assigns about 30 people to each project for one or two nights.
Season‑long effort
Planning begins months in advance, often nearly a year before a display is installed. “Our entire company runs 24‑hour shifts,” Casterella explained, noting that the effort will continue for the next 10 to 15 days as the season ramps up.
American Christmas employs engineers, designers, welders and builders who develop concepts starting in January and February, move to engineering in March, and place orders in April. By late September, crews are already hanging lights and constructing large‑scale decorations.
Scale of the operation
When the holiday season ends, more than 2,500 truckloads of equipment will have rolled into the city, and over 400 projects will be completed across the tri‑state area. Nationwide, the firm expects to finish more than 800 projects bearing the American Christmas name.
Among the most recognizable installations is the Radio City Music Hall display, a client for over 20 years. The venue’s 64‑foot tree features 50,000 LEDs. The FOX News Christmas Tree required 36 hours to build its frame and branches and now shines with 48,000 LEDs and thousands of ornaments designed to withstand wind and weather.
Local families enjoy the magic
Florida mother Kate Rankin, who travels to New York each year, says the city’s decorations offer a “once‑in‑a‑lifetime opportunity” and a chance to share the tradition with her children. Casterella notes that many visitors reminisce about seeing the lights with their parents as children.
American Christmas spends about nine weeks installing the city’s holiday displays and three weeks taking everything down, beginning the day after Christmas.