Taos Municipal Schools announced that it could start soliciting community input on the design of a new middle school as early as December. The project is the largest component of the $50 million general‑obligation bond that voters approved in November 2024.
Planning Phase and Funding
The New Mexico Public School Facilities Authority (PSFA) is recommending contractors for the initial planning stage and is actively looking for ways to rein in construction costs. One option under review is whether other northern New Mexico districts that are rebuilding schools could share building designs or use alternative contracting methods.
Superintendent Antonio Layton Jr. acknowledged the emotional weight of replacing a school with “50 years’ worth of history,” but said the district will honor the past by preserving some of the existing murals.
During the Bond Implementation and Oversight Committee meeting on Nov. 18, PSFA planning and design manager Claude Morelli said the agency hopes to finish preliminary assessments by the end of June 2027, if not sooner. The district will cover 63 percent ($155,925) of the $247,500 planning‑and‑assessment cost, with the state providing the remaining $91,575.
Design Goals and Site Options
The GO bond supplies $50 million in local funds and $30 million in state matching funds for long‑delayed facilities work. Senate Bill 131 raised the district’s state‑matching rate from 6 percent to 37 percent through 2027.
Last year PSFA ranked Taos Middle School 11th statewide in need. The existing 90,000‑square‑foot building was built for 1,100‑1,200 students, roughly three times its current enrollment.
Architect Doug Patterson of Living Designs Group estimates a “right‑sized” middle school would be about 60,000 square feet, designed for 315 students in grades six through eight. One potential site is undeveloped district property uphill from the current school, near homes on Calle Palomita. Building there would avoid the expense of using portable classrooms for two to three years.
Cost‑Saving Measures
PSFA has obtained surveying quotes from Bowman Consulting Group Ltd. and Bohannan Huston Inc., favoring Bowman for its lower price. The agency also engaged Southwest Title to check for easements or other property restrictions that could delay construction.
Morelli stressed the importance of avoiding surprises during design and construction, noting that once designers are on‑site, “it’s very expensive to stop the process.” Surveying could take roughly three weeks, while determining educational specifications may take considerably longer.
PSFA recommends the district contract with ARC, a firm that has previously worked with Taos, rather than Visions in Planning for the specifications phase. The process will involve teachers, administrators, students, parents and community members.
The state is relying on existing statewide purchasing agreements to sidestep lengthy requests for proposals amid rising construction costs. Morelli added, “We’re trying to get as much of this done as quickly as possible, but also as carefully as possible.”
Exploring Design‑Build Options
The district is also interested in a design‑build contracting method, where a single contract covers both design and construction. PSFA is exploring whether prototype designs could lower costs for districts rebuilding schools in Questa, Mora and Española.
Public Oversight and Transparency
The project follows a forensic audit that uncovered former facilities director Robert Valencia’s misdirection of $244,124 in public funds to his private family business, All Around Fence. Superintendent Layton emphasized that involving the Bond Implementation Committee in purchasing decisions is essential to maintaining taxpayers’ trust.
“Transparency information will be shared with the public, given that they still entrusted us with their money,” Layton said. Middle‑school principal Linda Martinez suggested issuing quarterly progress reports for residents who cannot attend meetings. The district plans to post meeting links on its website.
The next Bond Implementation Committee meeting will be held via Zoom on Dec. 8 at 5 p.m.