For the fourth straight Thanksgiving, passengers at Albany International Airport (ALB) are navigating ongoing construction that has stretched well beyond the original early‑2025 completion target. The delays affect roughly 70,000 travelers expected to pass through the airport between the Tuesday of Thanksgiving week and the following Monday, according to CBS6 Albany.
Airport CEO Stephen Clark said a large crane that has dominated the skyline will be removed soon, and four lanes of traffic outside the terminal will be opened as a temporary measure to ease congestion. Clark also highlighted recent improvements, including a renovated Concourse A and expanded TSA security queue space, while noting that the new departure hall—connected to a parking garage and a new Dunkin’ Donuts—remains under construction.
Regular flyers have felt the impact of the prolonged work. “Occasionally, there’s a difficulty with parking,” said Statia Darre of Queensbury, a monthly business traveler, adding that the situation is improving. Darre expressed relief at not having to fly over the holiday, noting, “Probably chaotic, but I don’t have to worry about that. I don’t come back until December.” She remains optimistic about the eventual improvements, saying, “I’ll be excited to see everything flowing smooth. I have no idea when it’s going to be done.”
The project’s timeline has shifted dramatically. Ground was broken in 2023 with an early‑2025 finish promised, but by the end of 2026 the airport is still under construction. Clark now estimates completion around “mid‑2027.” He attributed the setbacks to the project’s complexity, which has required redesigns to ensure a cohesive and safe passenger experience.
Complicating matters, MLB Construction, the firm overseeing the build, has filed a lawsuit alleging the airport breached its contract. The suit claims “design deficiencies” have extended the schedule by more than two and a half years and forced MLB to incur additional costs. MLB reports over 2,000 design revisions, describing them as “incomplete and uncoordinated,” and says the delays cost the company $8,000 per day. The company is seeking more than $12 million in damages.
Clark acknowledged the rising costs, stating the final price tag will exceed the originally announced $100 million. He emphasized that the additional funding will come from existing airport sources, not from taxpayers. “We won’t be going to taxpayers to ask for those dollars,” he said.
Despite the legal dispute, Clark said both parties remain committed to collaboration. The airport has held one meeting with MLB and has three more scheduled, with the shared goal of completing the project. “The parties continue to collaborate. We continue to work together to try to get the project done,” Clark affirmed.
What’s next: Albany International Airport aims to finish the renovation by mid‑2027, with ongoing coordination meetings between the airport and MLB Construction to resolve design issues and keep the project on track.
Sources: cbs6albany.com, cbs6albany.com