ALBANY, N.Y. – For the fourth consecutive Thanksgiving, passengers at Albany International Airport (ALB) are navigating a maze of construction zones, temporary traffic lanes and a towering crane that is slated for removal soon. Airport CEO Stephen Clark says the massive renovation, originally slated for early 2025, will not be finished until mid‑2027 and will cost well beyond the $100 million budget first announced.
What travelers are seeing now
Clark explained that a large crane will be taken down and four lanes of traffic outside the terminal will be opened to ease congestion for the roughly 70,000 passengers expected between Thanksgiving Tuesday and the following Monday. Regular flyers have noted the changes over the past four years. “Occasionally, there’s a difficulty with parking,” said Statia Darre of Queensbury, who flies for business each month. “But that’s also getting better,” she added, adding relief that she will not be traveling over the holiday.
Project timeline and cost outlook
Ground was broken on the expansion in 2023 with an early‑2025 completion target. As of late 2026, the airport still faces extensive work. Clark now describes the anticipated finish as “mid‑2027.” He highlighted recent progress, including a renovated Concourse A and expanded TSA security queue space, but noted that the centerpiece—a new departure hall linked to a parking garage and a new Dunkin’ Donuts—remains under construction.
“I think a lot of it has to do with the complexity of the project,” Clark said during a recent tour. “That results in the need for folks to pause and redesign certain areas to make sure that the experience is cohesive and safe.”
Legal dispute adds pressure
The airport is also contending with a lawsuit from MLB Construction, the firm overseeing the build. MLB alleges the airport breached its contract, citing “design deficiencies” that have pushed the schedule out by more than two‑and‑a‑half years and cost the contractor millions in additional work. The company claims over 2,000 design revisions have caused “cascading disruption and delay,” costing it $8,000 per day and prompting a claim for more than $12 million.
Clark acknowledged the numerous change orders but defended them as normal for a project of this scale. “There certainly were a lot of changes to this project, but you know again, complex projects are going to have change orders, it’s not something that’s abnormal,” he said.
Funding and next steps
When asked about the ballooning price tag, Clark confirmed the final cost will exceed the original $100 million figure. “But we’re not going to be going to taxpayers to ask for those dollars. We will be able to cover all of that using our existing funding sources,” he said.
Clark also noted that the airport has met with MLB Construction once and has three more meetings scheduled. He emphasized that both parties share the goal of completing the project. “The parties continue to collaborate. We continue to work together to try to get the project done,” he said.
What this means for the community
For Albany residents and business travelers, the extended timeline means continued inconvenience but also the promise of a modernized terminal that will better serve the region’s growing air traffic. The airport’s leadership remains confident that the final product will deliver a safer, more efficient travel experience once the construction is finished.