By OBBM Network Editorial Staff
Derived from an episode of American Energy Works.
When a towering steel lattice appears on the horizon of a family ranch, the excitement of progress quickly turns into a legal battle over who truly owns the land beneath it.
From Magna Carta to Texas Law: The Evolution of Eminent Domain
Nick Laurent traces the power of eminent domain back to the Magna Carta, noting that “there have been takings of private property for centuries, going all the way back to the Magna Carta and perhaps before.” In the United States, the Takings Clause was added to the Bill of Rights in the late 1700s, embedding the principle that government may take private property only for a public use.
Laurent describes the doctrine as “a necessary evil” that enables essential public works such as streets, fire stations, and schools. Yet he emphasizes that the modern application has expanded, allowing private utilities to invoke eminent domain when projects are deemed to serve the public interest.
The 765 kV Transmission Project: Scope and Controversy
The current controversy centers on a massive 765‑kilovolt transmission line slated to cut across Texas, affecting family ranches, farms, homes, and small businesses. The project is promoted as a solution to move “weather‑dependent electricity” into the Permian Basin, a region rich in natural gas resources.
Laurent points out that the Public Utility Commission (PUC) has already determined the projects—Dinosaur to Longshore, Longshore to Drillhole, and Howard to Solstice—”were needed and are necessary.” However, critics argue that the lines are intended primarily to serve major industrial users, not residential customers, and question whether the necessity of the lines has been adequately proven.
Compensation for Easement Takeovers
When a utility easement is taken, compensation typically includes three components. First, the value of the easement itself—Laurent uses a “one acre easement” as a round‑number example. Second, the “cost to cure,” which covers hard costs to restore the property, such as relocating a water well that lies in the easement’s path.
Third, “remainder damages” reflect any loss in value to the remaining property. “There is diminished value caused by the acquisition of the easement,” Laurent explains, noting that appraisers may assign a percentage—5, 10, or 15 percent—of the remaining property’s value as compensation. While some utility appraisers said remainder damages are negligible, landowner‑retained appraisers often disagree, arguing that the loss can be significant, especially on large parcels.
Legislative Action and the Role of the PUC
Texas lawmakers have voiced concerns about the 765 kV lines. HB 5066, the Permian Basin Reliability Plan, does not explicitly mandate cross‑state transmission lines, prompting legislators to urge the PUC to pause the projects pending further review.
Laurent notes that the PUC, as an administrative body, has discretion to proceed, but “the only way that the legislature could actually act and force a change would be to convene a special session.” Governor Abbott has not called such a session, leaving the projects on track for implementation. “It would be great to see that happen,” Laurent adds, urging continued pressure on legislators.
What Landowners Can Do Now
Landowners facing survey agreements from the utility company Encore can negotiate terms, setting limits on when survey crews may access their property and securing small rights. While many assume eminent domain is a last‑resort tool, Laurent cautions that misunderstandings abound, and property owners should actively engage in the process to protect their interests.
He advises landowners to seek independent appraisal of both the easement value and any remainder damages, ensuring that compensation reflects the true impact on their property. Engaging legal counsel familiar with Texas’s 2011 Senate Bill 18—known as the Texas Landowners Bill of Rights—can also provide additional protections beyond the federal framework.
As the PUC moves forward, the balance between statewide energy needs and individual property rights remains a contested arena. Whether Texas legislators will intervene before the next regular session could shape the fate of the 765 kV lines and set a precedent for future infrastructure projects.
The full episode of American Energy Works is available on OBBM Network TV.
Texans Face Massive Power Line Project: How Eminent Domain Impacts Property Rights
By OBBM Network Editorial Staff
Derived from an episode of American Energy Works.
When a towering steel lattice appears on the horizon of a family ranch, the excitement of progress quickly turns into a legal battle over who truly owns the land beneath it.
From Magna Carta to Texas Law: The Evolution of Eminent Domain
Nick Laurent traces the power of eminent domain back to the Magna Carta, noting that “there have been takings of private property for centuries, going all the way back to the Magna Carta and perhaps before.” In the United States, the Takings Clause was added to the Bill of Rights in the late 1700s, embedding the principle that government may take private property only for a public use.
Laurent describes the doctrine as “a necessary evil” that enables essential public works such as streets, fire stations, and schools. Yet he emphasizes that the modern application has expanded, allowing private utilities to invoke eminent domain when projects are deemed to serve the public interest.
The 765 kV Transmission Project: Scope and Controversy
The current controversy centers on a massive 765‑kilovolt transmission line slated to cut across Texas, affecting family ranches, farms, homes, and small businesses. The project is promoted as a solution to move “weather‑dependent electricity” into the Permian Basin, a region rich in natural gas resources.
Laurent points out that the Public Utility Commission (PUC) has already determined the projects—Dinosaur to Longshore, Longshore to Drillhole, and Howard to Solstice—”were needed and are necessary.” However, critics argue that the lines are intended primarily to serve major industrial users, not residential customers, and question whether the necessity of the lines has been adequately proven.
Compensation for Easement Takeovers
When a utility easement is taken, compensation typically includes three components. First, the value of the easement itself—Laurent uses a “one acre easement” as a round‑number example. Second, the “cost to cure,” which covers hard costs to restore the property, such as relocating a water well that lies in the easement’s path.
Third, “remainder damages” reflect any loss in value to the remaining property. “There is diminished value caused by the acquisition of the easement,” Laurent explains, noting that appraisers may assign a percentage—5, 10, or 15 percent—of the remaining property’s value as compensation. While some utility appraisers said remainder damages are negligible, landowner‑retained appraisers often disagree, arguing that the loss can be significant, especially on large parcels.
Legislative Action and the Role of the PUC
Texas lawmakers have voiced concerns about the 765 kV lines. HB 5066, the Permian Basin Reliability Plan, does not explicitly mandate cross‑state transmission lines, prompting legislators to urge the PUC to pause the projects pending further review.
Laurent notes that the PUC, as an administrative body, has discretion to proceed, but “the only way that the legislature could actually act and force a change would be to convene a special session.” Governor Abbott has not called such a session, leaving the projects on track for implementation. “It would be great to see that happen,” Laurent adds, urging continued pressure on legislators.
What Landowners Can Do Now
Landowners facing survey agreements from the utility company Encore can negotiate terms, setting limits on when survey crews may access their property and securing small rights. While many assume eminent domain is a last‑resort tool, Laurent cautions that misunderstandings abound, and property owners should actively engage in the process to protect their interests.
He advises landowners to seek independent appraisal of both the easement value and any remainder damages, ensuring that compensation reflects the true impact on their property. Engaging legal counsel familiar with Texas’s 2011 Senate Bill 18—known as the Texas Landowners Bill of Rights—can also provide additional protections beyond the federal framework.
As the PUC moves forward, the balance between statewide energy needs and individual property rights remains a contested arena. Whether Texas legislators will intervene before the next regular session could shape the fate of the 765 kV lines and set a precedent for future infrastructure projects.
The full episode of American Energy Works is available on OBBM Network TV.
Watch the full episode:
OBBM Network Editorial Staff
[email protected]Editorial team behind OBBM Network — independent, hyper-local journalism syndicated through HyperLocalLoop and OBBM Network TV.
Recent News
President Trump Orders Military Pause on Iowa Lead Explosives Detonation
President Trump Orders Military Pause on Iowa Explosives Detonation Amid Environmental Concerns
Jonesboro Municipal Airport to Celebrate Completion of 500‑Foot Runway Extension
Trending
President Trump Orders Military Pause on Iowa Explosives Detonation Amid Environmental Concerns
Jonesboro Municipal Airport to Celebrate Completion of 500‑Foot Runway Extension
Schmidt Bakery Stops Nationwide Shipping of Cherry Thing-a-Lings, Keeps Local Pickup for Presidents Day Event
Community News
Thanksgiving travelers at T.F. Green hope for smooth flights amid recent airline glitches
Warm Springs Museum launches 2026 year‑end fundraising campaign to preserve tribal heritage
The Rescue Mission launches 24‑hour “Living Room” livestream to tackle homelessness in El Paso
Soak House Warwick Turns Up the Heat on Post-Swim Recovery
Douglas Middle School teacher runs 113 miles to support Native American youth