Uniontown residents and neighboring communities will hear testimony on a draft data‑center ordinance at a public hearing scheduled for 10 a.m. on Dec. 11 in the Fayette County Commissioners’ meeting room. The ordinance, which would allow data‑center facilities in the county’s M‑1 (light industrial) and M‑2 (heavy industrial) zones, sets standards for buffer areas, a decommissioning plan and noise limits, according to the Herald‑Standard.
Under the draft, sound from a data center would be limited to 60 decibels between 9 a.m. and 7 p.m., and to 55 decibels after 7 p.m. The proposal also removes a previously required minimum tract size of 200 acres, a change that some residents say could bring larger facilities closer to homes.
Connellsville resident Tom Fosbrink told the commissioners that the final draft “weakens protections” that were in earlier versions. He noted that an earlier requirement for developers to provide an alternative‑site analysis was omitted, and that the definition of “sensitive receptors” was narrowed. The original draft listed any lawfully occupied dwelling, while the current version limits the term to schools with 20 or more in‑person students, hospitals and publicly owned parks.
Other community members echoed concerns about potential impacts on local roads and the lack of transparency in negotiations with data‑center developers. Business owner Aaron Zolbrod said, “We need to negotiate a good deal, and we don’t know if it’s a good deal when they don’t tell us anything,” adding that trucks could damage roads without a dedicated cleanup fund.
County officials defended the draft as a balanced approach. Commissioner Harry Kaufman said the ordinance “will protect residents” and that the board can still adjust items before final approval. Vice Chair Vince Vicites referenced a blueprint inspired by a Loudoun County, Va., commissioner, emphasizing the need to avoid overly restrictive rules that could lead to lawsuits.
Chairman Scott Dunn clarified that the board has not met with any data‑center developers nor signed non‑disclosure agreements related to site selection, noting that the only NDA signed to date was with the Fay‑Penn Economic Development Council for potential future discussions.
The public hearing on Dec. 11 will allocate the remainder of the day for community comment, giving residents a direct voice in shaping the final ordinance. The full draft can be reviewed online at the link provided by the Herald‑Standard.
What’s next: Residents are encouraged to attend the Dec. 11 hearing at 10 a.m. in the commissioners’ meeting room to submit comments. The board will consider public input before voting on the ordinance at its December meeting.