Ahwatukee homeowners have taken legal action against the City of Phoenix, filing an $11 million notice of claim that alleges the city violated its own zoning regulations to accommodate a sprawling data‑center complex. The lawsuit, filed Friday, claims the city failed to hold a proper zoning hearing before converting the site from commercial to industrial use.
Project details and resident concerns
The data‑center consists of five buildings covering roughly one million square feet and is located near 48th Street and Thistle Landing. Construction began in April and has continued despite growing opposition from nearby residents.
Many families live within a short distance of the site. Long‑time Ahwatukee resident Annette Poleon, who built her home on 47th Way in 1993, worries the development could force her family to leave the neighborhood that has been their home for more than three decades. “It’s sad to think that we may not be able to do this much longer,” Poleon said, adding that she feels “hopeless” and “helpless.”
Other neighbors echo her concerns. Michelle Settle cited potential strain on water supplies, electricity demand, internet bandwidth and noise levels, while Ana Marshall questioned how the project could proceed without any consequences for those living nearby.
Legal arguments
Attorney Anthony Ramirez, representing the Ahwatukee Community Alliance, argues that the city never conducted a zoning hearing to change the land’s designation from commercial to industrial. He also points to Phoenix’s data‑center ordinance, adopted in July 2025, which requires a special permit for new data‑center facilities. Ramirez says the project was improperly exempted from that ordinance.
According to Ramirez, the preliminary site‑plan approval for the data‑center expired in May 2026, yet the city granted final approval only about 20 days later, effectively sidestepping the ordinance’s requirements. “This is an industrial project on a commercially zoned lot, no one knew what was coming,” said resident Ana Marshall, adding that the city should be held accountable.
City response and next steps
The City of Phoenix has not responded to requests for comment. The lawsuit seeks damages for alleged violations and aims to halt further construction until proper zoning procedures are followed.
Local officials and planners will likely need to address the residents’ claims in upcoming city council meetings, where the issue of balancing economic development with community impact will be front and center. The outcome could set a precedent for how Phoenix handles large‑scale technology projects in residential neighborhoods.
What this means for Ahwatukee
For families like the Poleons, the dispute underscores a broader anxiety about rapid development and its effect on property values, quality of life, and the traditional character of the Ahwatukee community. As the legal process unfolds, residents hope the city will respect zoning laws and prioritize the well‑being of long‑standing neighbors.