At its regular meeting on November 19, the Harris County Emergency Services District No. 9 (ESD 9) board of commissioners discussed delaying the construction of the planned Station 16. The decision reflects a projected $3.89 million shortfall for the fiscal year 2026‑27, which the board attributes to a tax rate that does not keep pace with the rapid growth of the Cy‑Fair community.
Fiscal pressures drive the delay
Fire Chief Amy Ramon warned that, without a delay and at the current tax rate of $0.045 per $100 of home valuation, the Cy‑Fair Fire Department (CFFD) would be unable to cover the additional personnel costs associated with four upcoming stations. Three of those stations, she said, “cannot be put on pause.” While the department will continue planning for Station 16, the board will halt the process when it comes time to issue the construction bid.
Commissioners’ rationale
Commissioner Cameron Dickey called the postponement “extremely responsible,” noting that proceeding without sufficient funds would force the board to recommend a project it could not afford. Dickey labeled the funding gap “self‑inflicted,” pointing to the board’s decision to set a tax rate that falls short of the community’s expanding fire‑service needs.
The commissioners voted to table the Station 16 item to gather more information on potential construction‑cost differences should the delay be pursued. Dickey said these discussions are not surprising, as similar budget conversations occurred during the FY 2026‑27 budget process.
Budget context
Earlier this year, the ESD 9 board approved the FY 2026‑27 budget by a 3‑1 vote, acknowledging the projected shortfall. The shortfall stems in part from anticipated personnel costs for two upcoming fire stations, as reported in previous Community Impact coverage.
Station 16 is one of four future stations currently in design or construction as part of CFFD’s expansion plan, which aims to add eight stations overall to match the area’s growth.
Other board actions
During the same meeting, Commissioners Daniel Arizpe, Naressa MacKinnon and Cameron Dickey were sworn in for four‑year terms. In a unanimous vote, the board approved an increase to Chief Ramon’s annual salary to bring it in line with competitive pay, noting that her previous salary fell below the bottom 10th percentile. Commissioner Jaime Martinez praised the raise as “important for the well‑being of ESD 9.” The salary adjustment will not affect the FY 2026‑27 budget.
Looking ahead
The board scheduled its next regular meeting for December 17 at 6:30 p.m. in the District Administration Building at 10710 Telge Road. Residents can expect further updates on the Station 16 timeline and any additional budget measures aimed at closing the shortfall.
For now, the decision to delay the construction bid underscores the board’s commitment to fiscal responsibility while still recognizing the community’s need for expanded fire‑protection capacity.