Union County officials and local residents will be watching closely as Florida‑based Z Squared moves forward with plans to enlarge its artificial intelligence (AI) campus near El Dorado. The company’s subsidiary, Paradox Data LLC, secured an exclusive five‑year option on approximately 89.56 acres that border its current 3‑acre site.
Option terms and next steps
Under the agreement, Z Squared can initially purchase up to 10 acres after completing a survey and site investigations. The price for the first 10 acres is set at $20,000 per acre, with a $10,000 deposit already credited toward the purchase price. Any additional acreage would be priced at $33,333.33 per acre. Paradox Data paid Lerro Energy Group LLC a $37,500 consent fee and the first $10,000 annual option fee to make the agreement effective.
The option replaces an earlier arrangement that required the purchase of up to 10 acres by Dec. 23, extending the company’s rights to acquire more land over the next five years. Z Squared completed its acquisition of Paradox Data on Sept. 8, gaining full control of the Union County operation.
Local government context
In June, the Union County Quorum Court voted unanimously for a one‑year moratorium on data‑center construction after residents voiced concerns about potential impacts on local utilities and water resources. The moratorium was intended to give officials time to study the effects of data centers and consider appropriate regulations. The ordinance can be extended or rescinded by the court, but it remains unclear how the pause will affect Z Squared’s expansion plans.
Power and infrastructure considerations
Z Squared’s existing campus already has an electric service agreement with Entergy Arkansas for up to 8 megawatts of interruptible power. The company’s long‑term vision calls for up to 150 megawatts of AI‑ready capacity, but it acknowledges that additional electricity has not yet been secured. During a June Quorum Court meeting, an Entergy representative noted that Paradox Data had not yet contacted the utility about increasing demand.
The company’s CEO, David Halabu, said, “The industry has bought the chips. What it can’t find fast enough is power and a place to plug them in. That gap is the opportunity Z Squared is built for. We already have power on site at Union County and we’re securing the rights to this additional land now in anticipation of future tenant needs.”
Financial and regulatory outlook
In its SEC filing, Z Squared disclosed that substantial additional capital will be required to support its AI infrastructure strategy. The filing also noted that the company might not exercise the land option or complete a purchase, depending on financing, customer commitments, permits, and construction timelines.
County Judge Mike Loftin said he was unaware of the proposed project until a reporter contacted him, and residents have raised questions about the potential effects on electricity, water resources, and nearby properties. A Lerro Energy representative indicated that no agreements had been reached to sell land beyond the original 3‑acre parcel, though Z Squared’s filing references a binding letter of intent for up to 10 additional acres.
Potential impact on the local economy
While the company has not identified confirmed tenants or provided a construction timeline, the expansion could create new jobs and attract technology firms to the region. Z Squared has hired Atlanta‑based A2 Advisors to assist with development and tenant recruitment, signaling a serious effort to bring AI‑related businesses to Union County.
Local stakeholders will continue to monitor the situation as Z Squared works through power negotiations, financing, and regulatory approvals. The outcome will shape how Union County participates in the growing AI and data‑center industry while balancing community concerns about utilities and resources.
Original reporting: Texarkana Gazette — read the source article.