Taos officials announced that the ice rink at the Taos Youth and Family Center, which has been out of service since a roof fire on August 3, 2024, is slated to be finished by March 2027. The town emphasized that the project will not be rushed; it will be completed “right” to ensure a long‑lasting facility for the community.
Rebuilding from the ground up
During a site tour on November 16, technicians were seen laying steel and piping over fresh insulation and a vapor barrier. A new ice plant, described as a “giant air‑conditioning unit,” was delivered from Canada and will replace the old system.
“I want it done right,” said Taos Parks and Recreation Director Melissa Vigil. “Once it’s done right is when we’ll open.” Vigil stressed that the town will not “kick the can down the road” and that the investment, though costly, will provide a durable solution.
Project management and schedule
Project manager Brian Cribbin noted that many residents have been affected over multiple hockey seasons. In an email dated November 18, Cribbin reiterated the March 2027 target, adding that while the date is not firm, town staff, CIMCO, and subcontractors Jam Dig and TLC are working hard to improve the schedule.
Technical upgrades
The fire caused extensive water damage, turning the rink’s interior into a “pond” that froze into a permafrost effect beneath the slab. The new floor includes heated lines that keep the sub‑floor at about 40 °F, preventing future freeze‑induced heaving. Over 1,300 fused plastic joints will be pressure‑tested before the surface cement is poured.
The new ice plant uses carbon dioxide instead of the previous brine‑and‑glycol mixture and is roughly three times larger than the old unit, which operated on two compressors. Because the rink is not fully enclosed, adequate cooling is essential to avoid soft or wet spots on the ice.
Future ribbon‑cutting ceremony
Town officials plan a ribbon‑cutting celebration once the rink is ready for public use.
Pool closure and replacement
In addition to the rink, the main pool remains closed “until further notice” after the aging sand filter failed to maintain proper water chemistry. On November 10, the Town Council approved $408,221 to replace the filter tank built in 2004. The new solution will involve cutting a 6‑by‑6‑foot opening in an exterior wall, installing an insulated roll‑up door, and removing the old tank piece by piece.
Two smaller, automatically backwashing filters will replace the single large unit, allowing staff to service them more easily. The pool closure is expected to last two to three weeks in December, pending part availability and installation timelines.
Additional aquatic center challenges
The kiddie and therapy pools also stay closed because their ultraviolet sanitation bulbs are no longer manufactured. The town is seeking a domestically produced UV system to meet state requirements.
Staffing shortages further strain the aquatic center, which currently has no aquatic supervisor and only four employees, two of whom are part‑time lifeguards. The department is hiring and training new lifeguards to meet American Red Cross standards.
Community impact
The Taos Tiger Sharks swim team, without a backup pool, currently has nowhere to train. Team leader Richard Sanchez expressed concern, noting the club still has coaches to pay and is accepting donations.
Public stakeholder meetings for the Parks and Recreation Department continue on the third Wednesday of each month at 5:15 p.m. in the Youth and Family Center, providing residents a venue to stay informed and voice concerns.