The New Haven City Plan Commission voted unanimously on Wednesday to approve EG Home’s site‑plan, inland‑wetlands and sediment‑control applications for a 64‑unit townhouse development on the former Townshend estate. The project will span 12 acres of the 26.25‑acre property at 725 Townsend Avenue, adding 16 buildings and 155 parking spaces.
Local leadership frames the project as a homeownership opportunity
Commission members highlighted the public‑benefit of additional housing. Patricia King noted that “additional housing certainly is a public benefit,” satisfying the inland‑wetlands review criteria. Chair Adam Marchand added, “I think additional housing is a substantial public good and social benefit.” The applicant’s attorney, Ben Trachten, called the plan “a complete plan” and emphasized that development is a trade‑off, offering families the chance to own homes priced around $600,000‑$700,000.
Project details and environmental safeguards
The steep, forested site slopes from 161 to 81 feet and contains Class C inland wetlands. City Plan Director Laura Brown said the plan includes more than 31,000 cubic yards of soil movement, a retaining wall, and deck footings placed at least 50 feet from the wetland’s Upland Review Area. The commission’s recommendation reflects confidence that the retaining wall and decks will have minimal impact on the wetlands.
Community response
Neighbors expressed concerns about traffic and the loss of mature trees. Louis Viscuso warned that the 12‑acre wooded area “has been untouched for all these years for a reason” and feared increased road traffic. Maureen McLeggon and Jeff Fuller worried the project could face delays similar to the nearby 11‑unit development at 745 Townsend.
Supporters countered that the development will revitalize a long‑idle portion of the estate. Chuck Mascola, one of the current owners, said EG Home is “the most reputable and most accomplished building doing business in Connecticut right now.” Harvey Townshend, an eighth‑generation descendant of the estate’s original family, acknowledged the desire to preserve the woods but noted the practical reality of nearby airport noise and the need for progress.
Timeline and next steps
Chris Oliveira, EG Home’s vice president of land development, projected a two‑and‑a‑half‑year construction schedule. The plan calls for clear‑cutting the trees and installing a roadway within five months, followed by home construction.
Commission member Patricia King affirmed that the wetlands review was satisfied because the project provides a clear public benefit. Chair Marchand indicated the commission could request the removal of one or two units to adjust the retaining wall’s location, though such changes might increase financial risk.
Broader context
The approval reflects New Haven’s ongoing effort to increase housing supply while balancing environmental stewardship. By converting a historic estate’s unused forested land into affordable homeownership opportunities, the city aims to support families and strengthen the local tax base.
All approvals – inland wetlands, sediment control and site plan – were adopted unanimously, signaling strong municipal backing for the development.