The Louisiana Public Service Commission on Wednesday rejected South Louisiana Electric Cooperative Association’s (SLECA) request for a new hearing to abandon service to three coastal marsh areas in Lafourche and Terrebonne parishes. The commission had already approved SLECA’s exit from one of four targeted zones, Lake DeCade, but kept the remaining three – Lake Fields, Four Point Island and Grand Pass – in the utility’s network.
Why the decision matters for local camp owners
The four areas SLECA sought to abandon would affect roughly 282 properties that had electricity before Hurricane Ida struck in 2021. Most of those properties are fishing and hunting camps that rely on power for refrigeration, lighting and safety equipment. Without service, owners would be forced to depend on generators, an ongoing expense that many families cannot sustain.
Commissioners stress public‑service duty
Commissioner Eric Skrmetta (R‑Metairie) called SLECA’s business‑driven approach “unfair” to the camp owners. “SLECA is given a license, effectively, from the commission to provide service to all people in that region who seek service,” Skrmetta said. “They are not given a license to deny service to people in that area.” He added that if a residential neighborhood lost power, the utility would be required to repair lines and bill customers for the repair costs.
Commissioner Davante Lewis (D‑Baton Rouge) told SLECA’s lawyers the matter was settled and did not merit a rehearing. “I think it is very disingenuous to constantly throw the cost out there as a consideration of understanding why you didn’t comply with the September decision,” Lewis said.
Cost estimates and federal assistance
SLECA estimates that restoring power to the three remaining areas would cost upwards of $140 million, plus an additional $11 million to $23 million for environmental permitting and right‑of‑way acquisition. The Federal Emergency Management Agency (FEMA) has pledged to cover 90 % of the restoration expense, leaving the co‑op to seek a modest monthly charge of $13 to $24 from customers to offset its own costs.
Camp owners voice opposition
Camp owners testified against the rehearing request. Brent Story, a Houma resident who owns a camp in the affected zone, said, “I understand the whole co‑op would have to pay for us, but I’m part of that co‑op. I’ll be paying my share, as I have in the past when it wasn’t me that was being restored.” Sara Boudreaux, another camp owner, responded to a commissioner’s question about a dollar amount by stating, “Put my power back. Money is not equitable.” Commissioners noted that a generator settlement would only provide a temporary fix, as generators require fuel and regular maintenance.
Safety and erosion concerns cited by SLECA
SLECA argues that safety concerns and the difficulty of accessing the marshy terrain during emergencies justify its abandonment request. The co‑op points out that when the lines were first installed in the 1960s, the land was more stable. Ongoing coastal erosion, subsidence and repeated storm damage have made the area increasingly vulnerable.
Consumer group challenges cost figures
The Alliance for Affordable Energy, a consumer‑advocacy organization, contended that SLECA’s restoration cost estimates reflect the most expensive option available. The group claims the figures include replacing infrastructure that SLECA had already removed prematurely, such as lines that suffered only minor damage.
What’s next for the coastal camps?
With the commission’s decision, SLECA must move forward with restoring service to the three contested zones. The co‑op will work with FEMA and local stakeholders to secure the necessary permits and funding. Camp owners and local officials will continue to monitor the restoration timeline, emphasizing the importance of reliable electricity for safety, livelihood and the preservation of Louisiana’s coastal heritage.
Original reporting: KTBS 3 (Shreveport) — read the source article.