Demolition work began Monday on the former Brothers Lounge building in Omaha’s Blackstone neighborhood, a step that city officials say will clear the way for the ongoing streetcar project and future development of the site.
According to 3newsnow.com, crews arrived with equipment to prepare the structure for removal and expect to start dismantling the roof on Tuesday or Wednesday. Rather than using a wrecking ball, the demolition contractor will take the building down manually, piece by piece, because the property sits between two neighboring buildings, including the Colonial Hotel Apartments.
Le Nguyen, permits and inspection superintendent with the Omaha Planning Department, explained that the manual approach is typical for structures located between other properties. “Since it’s located between two neighboring property, usually, this is the process that the demo contractor would proceed with,” Nguyen said. She added that the Colonial Hotel Apartments are structurally independent, so the demolition will not affect that apartment building.
The city purchased the vacant building for $700,000 in September and has been monitoring a large hole that formed beneath part of the structure in June during streetcar construction on Farnam Street. Steve Jensen, interim director of the Omaha Streetcar Authority, said the purchase and demolition are intended to keep the streetcar project on schedule. “There were concerns that maybe this would hold up the construction of the streetcar,” Jensen said.
Nguyen estimated the demolition will take about a week to a week and a half, with two weeks as the upper limit. Once the building is fully removed, the hole will be filled and the site fenced off. The city also noted that several developers have expressed interest in acquiring the cleared lot for future projects.
City officials aim to have the entire building demolished by the end of next week, according to the same 3newsnow.com report. The rapid timeline reflects the city’s commitment to minimizing disruption to nearby residents and businesses while advancing the broader transit and redevelopment plans for the area.
What’s next: After demolition is complete, the city will fill the remaining hole and secure the property with fencing. Interested developers are expected to submit proposals for the site in the coming weeks, and the Omaha Streetcar Authority will continue its construction work along Farnam Street without further delay.
Sources: 3newsnow.com, 3newsnow.com