Casper residents will have the opportunity to weigh in on a revised renewable‑energy development when the Natrona County Board of Commissioners convenes on Tuesday at 3 p.m. in the second‑floor courtroom of the Natrona County Courthouse, 200 N. Center St. The meeting, which will also feature general business and public hearings at 5:30 p.m., will be streamed live on the county’s YouTube channel, according to oilcity.news.
The developers of the Dinosolar project are asking the board to amend two conditional‑use permits so construction of a smaller, single‑phase solar farm and battery storage facility can begin in March 2029. The new plan reduces the project’s footprint from 3,591 acres to 2,396 acres and scales the capacity to 240 megawatts, down from the originally proposed 440‑megawatt battery storage system, as reported by oilcity.news.
NextEra Energy Resources, which acquired Dinosolar LLC in 2023, cited “market changes and increases in utility connections and network upgrade costs” as the drivers for the downsizing. Project Director of Development Glenn Shober told the Planning and Zoning Commission that “constructing in one phase is better from a development standpoint,” a sentiment that the planning board unanimously endorsed on Oct. 13, according to oilcity.news.
The original $240 million project received county approval in June 2020 with an anticipated 2023 start‑up. A 2022 extension pushed the permit deadline to Dec. 2026 and added approval for the battery system. However, ongoing revisions have prompted the commissioners to explore legal options against the developer earlier this year, a move that has raised concerns about financial impacts on neighboring municipalities and the Natrona County Fire Protection District (NCFD), which planned to replace aging fire equipment using tax revenues from the project, oilcity.news noted.
County planning staff mailed notices to 332 neighboring property owners ahead of the hearing. Only one written objection was received—from Bar Nunn residents Tom and Shelley Whitmire. Two additional letters expressed support, one from a Casper resident and another from an Evanston resident, oilcity.news reported.
In addition to the Dinosolar agenda, commissioners will consider several other items on Tuesday’s docket: enlarging the Mile‑Hi Improvement and Service District to include two properties on Horseshoe Road; forming the Phillips Lane Improvement and Service District after a landowner petition; and designating 23.18 miles of County Road 212 (Gas Hills Road) as a county highway by prescription, oilcity.news said.
The consent agenda will also address a real‑estate trade agreement with the city of Casper, swapping six parcels—including sites near Casper Mountain Trails Center, Fort Caspar, Sage Park, and the Casper‑Natrona County Health Department—along with a waterline easement. Additionally, the board will approve Natrona County’s participation in the Albertsons opioid settlement, securing a 7.9 % share of the state’s $13.1 million recovery, and a $127,618 amendment to the county’s adult drug‑court opioid settlement contract, oilcity.news detailed.
What’s next: The public hearing on the revised Dinosolar project will take place on Tuesday at 3 p.m., with a follow‑up public hearing at 5:30 p.m. Residents can watch the proceedings live on the county’s YouTube channel. The board is expected to vote on the permit amendments later that day, potentially setting the timeline for construction to begin in early 2029.
Sources: oilcity.news